 |
| 10.4.05 |
|
|
 |
|
...HPC
BRIDGE VIEWS |
| 
|
|
Latest Edition Gives New Perspective on Design-Build Project
This issue of HPC Bridge Views focuses on one
design-build project from the perspectives of the owner, designer, general
contractor, and concrete supplier.
For its largest and most complex bridge project ever completed,
the South Carolina Department of Transportation set high design standards:
100 year service life at the lowest life-cycle cost. The design objectives
were met not only through the use of HPC, but also through a hig- performance
contract between the owner and the contractor.
The designer’s main challenge was that there was
no code to follow for a 100-year design. Through extensive research and
considerable engineering judgment, they devised a combination of low-permeability
concrete and minimum concrete cover to assure long service life. The use
of performance-based specifications allowed complete freedom to the contractor
to come up with the most economical concrete mix design.
Due to high performance requirements placement limitations,
the contractor was faced with the use of every imaginable placement technique:
hoppers, pumps, tremie concrete, and mass concrete. The excellent partnering
with the owner allowed the contractor to use the best technology to get
the job done.
The concrete supplier had his own challenges to produce
over 320,000 cu yd of concrete including high strength, high early strength,
low permeability, extended set times, extended transportation times, and
control of initial concrete temperatures. Again, the design-build process
allowed the flexibility to select the mix design to construct the best
bridge possible. The $531 million project was completed more than one
year ahead of schedule.
Click
here to download.
Click
here for past issues.
|
 |
|
...HIGH-PERFORMANCE
CONCRETE |
 |
|
HPC Works for Every-Day Bridges
High-performance concrete is not just for high-profile
megaprojects. You can use it for routine highway overpasses such as SR18
over SR516 in King County, Washington. For today's emphasis on construction
zone safety and reduced traffic delays, you can "stay out" by
building with maintenance free, long-lasting, and durable HPC.
Washington State Department of Transportation (WSDOT)
has developed and used high-performance concrete (HPC) mixes containing
fly ash and silica fume in several highway bridges since 1992. The concrete
has high compressive strength attaining 10,000 psi (69 MPa) by 28 days,
low chloride permeability averaging less than 1,000 coulombs by 56 days,
and generally lower shrinkage and creep values than conventional concrete.
More.
|
 |
|
...NEW
RESEARCH |
 |
|
Avoiding Strand Corrosion
Dr. Andrea Schokker of Penn State University recently
conducted research on the issue of strand corrosion in sealed environment.
The research found that:
- Corrosion could occur in a sealed environment despite the initial
high pH of the grout bleed water and the low levels of chlorides in
the system.
- The corrosion mechanism is most likely a carbonation reaction involving
carbon dioxide in the air and calcium hydroxide in the grout bleed water.
This reaction creates regions of low pH at the surface of the bleed
water where the passivity of the steel is lost and corrosion subsequently
occurs.
To avoid post-tensioned tendon corrosion due to grout bleed water, the following
recommendations are made:
- Measures should be taken to eliminate the bleeding of grouts used
in post-tensioned construction, even in traditionally noncorrosive environments.
High quality antibleed grouts should be used to ensure tendon durability.
The motivation for using bleed-resistant grouts has focused previously
on grout bleed voids as potential locations for chloride ingress and
subsequent corrosion initiation. The present research indicates that
even the presence of grout bleed water in the tendon can initiate corrosion
in the absence of chlorides.
- Post-tensioned tendon anchorage protection systems, which completely
encapsulate the anchorage hardware and strand ends, should be used to
prevent air, water, or chlorides from entering the tendon.
Click
here for the full report.
|
 |
|
...CONCRETE
BRIDGE CONFERENCE |


|
|
Bridge Tour Added to CBC
A site visit to the Galena Creek Bridge currently under construction will
take place on
Sunday, May 7, 2006 (1:00 - 4:30pm). When completed the main span of 689
ft. will be the longest concrete arch span in the U.S. The construction
of the arch will utilize an innovative method called the pilot truss method
in which a steel truss used as a support during construction becomes a
composite part of the completed concrete arch. Nevada DOT engineers will
be on hand to provide an overview of the project and answer questions.
The 2006 Concrete Bridge Conference will be held May 7-10, 2006, at the
Nugget Resort Hotel in Reno, Nevada, in conjunction
with the 2006 Post-Tensioning Institute (PTI) Technical Conference and
Exhibition. Your registration will enable you to attend both conferences.
More than 600 attendees are expected.
More.
|
 |
|
...IN
THE NEWS |
 |
|
SAFETEA-LU Becomes Law
Officially dubbed the "Safe, Accountable, Flexible,
and Efficient Transportation Equity Act: A Legacy for Users," the
new $286.4 billion, six-year highway bill was signed into law by President
Bush on August 10, 2005. The bill authorizes $16.5 million for research
and technology transfer of high-performance concrete bridges. PCA, the
Precast/Prestressed Concrete Institute, and other members of NCBC will
work closely with the Federal Highway Administration to achieve the objectives
set forth in NCBC's Building a New Generation of Bridges - A Strategic
Perspective for the Nation, the advocacy document produced in support
of the research program.
More.
|
 |
|
...SPECIAL
OFFER |
|

|
|
Take 1/3 Off New Guide Specification for High Performance Concrete
for Bridges
This guide specification is for all high-performance
concretes supplied for highway bridges, whether produced by a ready mix
supplier, a general contractor, or in a permanent plant of a precast concrete
manufacturer. The document provides mandatory language that the specifier
can cut and paste into project specifications. It also includes guidance
on what characteristics and limits should be specified to ensure satisfactory
performance for a given element or environment.
EB233—Regular
price $30
Now only $20 until October 31, 2005.
|
 |
|
...Q&A |
|
|
Question: What is match curing and can I use it to determine specified
release strengths and design strengths?
Answer: Match curing is a system in which
a standard concrete cylinder—usually 4x8 in. (102 x 203 mm)—is
cured at the same temperature as that measured in a concrete member. The
system includes a temperature sensor in the member, a controller, a special
insulated cylinder mold with a built-in heating system, and a temperature
sensor in the mold. Whether or not the match-curing technique can be used
to determine specified strengths will depend on the specifications. More.
|
 |
|
|
| |
|
PCA considers
mailing lists confidential; your information will not be sold or distributed,
nor will PCA use it for anything other than the stated purpose.
|
 |
|
Portland
Cement Association
5420 Old Orchard Road
Skokie, IL 60077
847.966.6200 • Fax: 847.966.9666
email: info@cement.org
|