Center
for Advanced Clinical Studies
The Methodist Hospitals
Merrillville, Indiana
Buildings Home > Case
Studies: Healthcare>The Methodist Hospitals The
Center for Advanced Clinical Studies creates a center of excellence for
the cancer and neuroscience programs at The Methodist Hospitals Southlake
Campus. This 3-story hospital plus basement addition contains 96,000 square
feet of space for both inpatient and outpatient departments. These include
Medical and Radiation Oncology, Neuroscience, Electrodiagnostics, Sleep
Lab, and Neurosurgery offices.
The project features two Linear Accelerator Vaults and a Gamma Knife
Vault. These rooms incorporate an average of 4-foot-thick cast-in-place
reinforced concrete walls and ceilings for heavy radiation shielding.
The hospital sought to “fast track” the Gamma Knife program
prior to the completion of the rest of the project, to establish the second
Gamma Knife installation in Indiana.
A concrete floor system was selected to allow matching floor elevations
with the original building, which also used a concrete flat slab. The
floor-to-floor height is 13 feet, 6 ¾ inches at the first floor,
and 11 feet, 9 ¾ inches on subsequent floors. The floor framing
was easily integrated with the massive concrete placements for the equipment
vaults.
Methodist Hospitals wanted to incorporate a ceiling HVAC system with
the latest in electrical and low voltage distribution, and getting adequate
ceiling height was a real challenge. With spans up to 30 feet, a 10-inch-thick
flat slab with 4-inch drop panels was designed to maximize the ceiling
plenum and allow up to 9-foot ceilings in some procedural areas on the
first floor. Careful coordination between M/E/P engineering systems was
essential to ensure success.
Concrete columns 20 inches square support the flat slab and are designed
to accommodate an additional floor of future vertical expansion. Concrete
shear walls were chosen to resist seismic and wind loads while controlling
drift and minimizing movement between the new and existing structures.
Another challenge was the original adjacent 26-foot-deep basement for
existing air handlers. The hospital wanted the new addition to match the
occupied basement depth of 15 feet, 6 inches below the first floor, but
also to have services fed from the deep basement. The typical new spread
footings were lowered along the existing deep basement to reduce lateral
pressure along the existing deeper foundation wall. A concrete service
tunnel was created for chilled water, medical gas, and sprinkler mains
fed from the main complex.
Construction began in December 2001, and concrete placements continued
throughout the typical blustery Northwest Indiana winter. The general
contractor was able to self perform the concrete work, assuring schedule
adherence. The Gamma Knife was operational by March 2002. For the three
vaults alone 1,480 cubic yards of concrete was used. The project is a
major success for the hospital, creating a new image for a state-of-the-art
program.
|
 |

Case Studies:
Cultural Buildings
Educational Institutions
Green Buildings
Healthcare
Hospitality
ICF Buildings
Luxury Residential
Mixed Use
Office Buildings
Religious Structures
Tilt-Up Buildings
| Owner:
The Methodist Hospitals
Architect/Structural Engineer:
HLM Design, Chicago, Illinois, and Bethesda, Maryland
General Contractor:
Berglund Construction, Chicago, Illinois
Formwork Contractor: CECO Concrete Construction
Concrete Supplier:
Smith Redimix
|
|
|