Buildings 
Home
 

Overview 

Design Aids 

Building  Presentations 

Software 
Solutions
 

Resources 

Technical 
Support
 

Regional  Contacts 


Southern Regional Women’s Center
Riverdale, Georgia

Buildings Home > Case Studies:Healthcare>Southern Regional Women’s Center

The Southern Regional Women’s Center project is the first of its kind, comprising 100,000 square feet in three stories of health delivery systems to women and newborns in the Riverdale and south Atlanta area. Tied into the existing hospital, the concrete structure has a brick facade and an ornamental entrance canopy cantilevered 30 feet from concrete columns. The interior is upscale with high-grade millwork and rich finishes. An open, 2-level atrium with a circular grand staircase serves as the interior focal point.

The $15 million Women’s Life Center features 8 ante-partum rooms, 10 labor and delivery rooms, 32 post-partum rooms, 4 triage rooms, 10 GYN beds, and a 12-bed NICU nursery. As patient volume increased steadily, the owner required the new project to be in operation as quickly as possible. Construction started January 2000 and then center opened, appropriately, on Mother’s Day 2001.

The project architect set stringent floor depth limits in order to maximize the ceiling cavity available in the floor-to-floor design height of 14 feet. A “skip joist” and beam system with conventional reinforcing was selected to span the 35 x 35-foot typical bays. The joist depth was limited to 16 inches and supported a 4?-inch-thick slab to provide the required 2-hour fire rating. In order to maintain a constant elevation for the floor bottom, the supporting beams were post tensioned to match the joist depth and were 24 or 36 inches in width.

Unlike the steel framing alternate considered for this project, the concrete floor system provided a constant bottom of floor surface to facilitate routing and installation of MEP utilities. It also eliminated the need for spray-applied or drywall fireproofing, which would have slowed down construction, added cost, and made future changes in piping and conduit more difficult. Actually the project team cooperated to locate and form the required number of sleeved openings and penetrations in the concrete floor. And in some instances, spare sleeves and penetrations were formed and capped in anticipation of future piping and utility needs. The upfront coordination paid off given the extensive nature of the MEP systems required to support over 40 upscale patient rooms.

Auger-cast piles 14 inches in diameter were used due to poor soil conditions at the project site. Typical 18-inch square columns were cast monolithically with the infill concrete walls in the terrace level underground and extended the full height of the building. Concrete shearwalls forming the stair and elevator shafts were designed to carry lateral wind loads. The 12-inch-thick wall elements and the building frame called for 4000-psi normal weight concrete, while the floor system utilized 5000-psi lightweight concrete to minimize the number of piles.

This hospital aimed to provide a feeling of rich southern comfort and hospitality and is delivering it with an attractive concrete building. Pre-construction studies by the contractor concluded that concrete was the economical option from a cost and schedule standpoint. With the shallow floor depth, no fireproofing, and a constant depth MEP ceiling cavity, concrete was clearly the way to go.




Case Studies:

Cultural Buildings
Educational Institutions
Green Buildings
Healthcare
Hospitality
ICF Buildings
Luxury Residential
Mixed Use
Office Buildings
Religious Structures
Tilt-Up Buildings


Architect:
CDH Partners
Marietta, GA

Structural Engineer:
Pruitt Eberly Stone Atlanta, GA

General Contractor:
R. J. Griffin & Company
Atlanta, GA

Concrete Contractor:
Harcon, Inc.

Concrete Supplier:
LaFarge



 
Careers | Sitemap | Disclaimer | Privacy Policy | © 2008 Portland Cement Association - All Rights Reserved