Borgata
Hotel Casino & Spa
Atlantic City, New Jersey
Buildings Home > Case
Studies: Hotels > Borgata The
Borgata Hotel Casino & Spa opened with a splash July 3, 2003. It is
the first new casino to hit the shores of Atlantic City in 13 years. The
4.1 million-square-foot complex comprises an impressive hotel tower, a
sizeable low-rise casino and spa, and a 5300-vehicle parking facility.
The buildings utilize three types of structural systems, each selected
to meet the needs of the specific structure. The tower is a post-tensioned,
cast-in-place concrete structural system, the low-rise uses a concrete-steel
composite construction, and the parking facility is precast concrete.
The Borgata features a 1.53 million-square-foot, 46-story, 2,400-room
hotel tower. An investigation of numerous structural systems for the tower
determined that post-tensioned cast-in-place concrete construction would
best suit the project’s needs. This system provided the lowest floor-to-floor
heights, the thinnest floor slab construction possible, and the most efficient
use of materials. It also offered the flexibility to adapt the structure
to meet the architect's design requirements.
A cylindrical zone at each end of the tower lends a unique architectural
appearance. Despite irregular column locations and numerous floor openings,
the circular floor areas in these zones are economically designed and
constructed with cast-in-place post-tensioned concrete. Spaced 35 feet
on center, the perimeter columns in the circular areas required an 8.5-inch-thick
slab. Designed as 8.5-inch-deep in-slab beams, the curved slab edges were
constructed with a curved band of tendons along the floor radius to support
a "mullion-free" glass curtain wall façade. Despite being
the thinnest floor system investigated for this project, the post-tensioned
floor was the best suited for meeting the stringent slab edge deflection
requirements established by the curtain wall manufacturer.
More than 79,000 cubic yards of concrete and 579 tons of post-tensioning
tendons were used in the hotel tower and low-rise casino superstructures.
Post-tensioned cast-in-place concrete construction provided the hotel
design team with flexibility to accommodate irregular column locations
and slab openings, curved slab edges, low floor-to-floor heights, and
stringent slab edge deflection requirements with efficiency and economy.
Read More:
The $1.1 billion, 4.2 million-square-foot resort includes a 43-story
tower on a 30-acre site with 3,100 trees. It features 2,002 guestrooms
and suites, 125,000 square feet of gaming space, parking for 7,100 cars,
and a 50,000-square-foot European-style spa. It has 11 retail boutiques,
11 restaurants, a 1,000-seat theater, a 15,000-square-foot indoor pool/garden
complex and 70,000 square feet of event space.
The unique shape of the hotel and strong winds off the Atlantic Ocean
meant that the building’s structural system had to be fine-tuned
using wind tunnel analysis. A wind tunnel study was conducted to investigate
the structure’s response to hurricane-force winds. Shear walls were
strategically located to best resist the wind loads, and 9000-psi concrete
was used in the walls.
The hotel tower utilized several concrete mix designs. The columns and
shear walls were constructed using concrete varying in strength from 9,000
psi on the lower floors to 5,000 psi on the upper floors. Higher strength
concrete on the lower levels greatly reduced the amount of reinforcing
steel required in columns and walls to eliminate rebar congestion and
expedite construction. The tower’s height, geometry, location on
a hurricane coastline, and distinctive full-height glass curtain wall
system necessitated the use of a sufficiently stiff lateral load resisting
system to prevent excessive building drift during hurricane-force winds.
Minimum modulus of elasticity values were specified and tested for each
of the specified concrete strengths to ensure the proposed mix designs
would yield the necessary concrete stiffness and strength. An investigation
of the concrete long-term creep and shrinkage was carried out to address
the differential shortening between adjacent columns and shear walls.
With a 5% material cost premium over conventional Grade 60 reinforcing
steel used for #10 bars and smaller, Grade 75 reinforcing steel was specified
for #11 and #14 bars. The extra cost helped reduce the amount of reinforcing
required by 20%.
Column sizes and locations were configured to optimize the design of
the floor slab, where the largest percentage of the hotel tower concrete
is contained. Framed with 5,000-psi, 7.5-inch-thick post-tensioned slabs,
the 510-foot-long floor was constructed without expansion joints and assisted
by the central location of the elevator core. Temporary pour strips divided
each floor slab into three independent segments to allow creep and shrinkage
shortening to occur in each segment for thirty days before joining the
floor plate together as an uninterrupted 510-foot-long slab. The pour
strips also allowed simultaneous construction of each floor in three segments
to facilitate post-tensioning operations. Slab tendons were banded along
the column lines in the short direction of the floor and were distributed
uniformly in the long direction. With a span of 30 feet, 9 inches in the
long direction, the slab achieves a span-to-depth ratio near 50. None
of the structural systems investigated during the project schematic design
phase came close to matching this value.
Attachment of the façade to the floor slabs required careful attention
to slab edge deflections and the means by which these deflections could
be controlled. Additional tendons were added at perimeter slab edges to
provide the required stiffness and to reduce dead-load and long-term-creep
deflections that would otherwise have occurred. In order to maximize efficiency
of the slab design, mild reinforcing steel was placed in the top and bottom
layers of the slab in the longer span direction. The uniformly distributed
tendons were given priority in placement over perpendicular mild reinforcing
steel, permitting installation with the maximum possible drape.
A massive, curved, staged post-tensioned transfer girder was required
on the tower’s third floor to support a 43-story-high tower column,
which architectural design dictated could not extend below level three.
The large concentrated load on the transfer girder required prestressing
force in the girder of 3000 kips. The tendons were stressed in several
stages as tower construction progressed. By gradually stressing the tendons
as loads increased on the girder, designers were able to keep stressed
within allowable limits. Perpendicular concrete beams were arranged to
brace the curved transfer girder against torsional rotation.
Columns were sized to be large enough so that the required floor slab
thickness was driven by flexural considerations and not slab punching
shear stresses around the columns. Slab openings were kept away from columns
wherever possible; however, when slab openings adjacent to columns could
not be avoided, prefabricated shear reinforcing was installed around the
columns. This slab shear reinforcing eliminated the need for drop panels
and allowed continued use of the most efficient slab thickness.
Architectural design in levels one and two below the hotel tower required
a shift in location of two shear walls. The level three floor slab was
designed as rigid diaphragm to transfer the horizontal shear wall forces
through the slab between the offset walls. A 16-inch post-tensioned slab
was used to provide the floor slab diaphragm with sufficient strength
and stiffness for lateral load transfer between the offset shear walls.
|
 |

Case Studies:
Cultural Buildings
Educational Institutions
Green Buildings
Healthcare
Hospitality
ICF Buildings
Luxury Residential
Mixed Use
Office Buildings
Religious Structures
Tilt-Up Buildings
|
Owner: Borgata
Architect:
BLT/Cope, Linder
Structural Engineer: Cagley Harmon & Associates
Construction Manager/General Contractor:
Yates/Tishman
|
|
|