Elysian Hotel & Private Residences
Chicago, Illinois
Buildings Home >
Case Studies: Mixed Use > Elysian
Introduction
Reinforced concrete was chosen as the structural system by the design
team for several important reasons on this residential building.
The floor to floor heights were minimized with the use of thin,
post-tensioned concrete slabs, which allowed the Owner to cost effectively
maximize the number of floors in the building. In addition, concrete
provided the necessary stiffness for the Outrigger-Braced lateral
system while providing the speed of construction necessary to meet
the project schedule demands.
Wind and its dynamic effects governed the structural design of
this 700 foot tall concrete residential tower. Originally conceived
as a 40 story tower – its concrete core and outrigger lateral
system and structural layouts were established, and then the height
was then extended to 61 stories. Recognizing the structure’s
stiffness would now not be sufficient to keep accelerations within
acceptable limits (the key for lateral design of tall towers) –
at least not without increasing costs substantially and yielding
impractical architectural space layouts – Halvorson and Partners
(HP) sought to economize the structure at hand and introduce a secondary
damping system to insure accelerations in the tower due to wind
met standard criteria.
With the assistance of the Boundary Layer Wind Tunnel (BLWT) Laboratory,
HP studied options for different combinations of structural stiffness
and damping to develop a cost effective structural solution that
incorporates a Tuned Liquid Damper (TLD) at the top of the building.
The TLD is the latest approach to controlling perceptible motion
in tall, slender buildings offering low cost, low maintenance and
high performance over a broad range of wind conditions. The Elysian
is one of the first residential towers in the United States to incorporate
this efficient technology.
Project Description
The
Elysian Hotel and Private Residences is 638,000 square feet of mixed-use
space with retail, parking, hotel, and condominium functions located
on E. Walton Place between Rush Street and State Street, just minutes
from Chicago’s iconic Magnificent Mile. The west side of the
site consists of a four-story (60 feet tall) steel structure above
grade containing retail facilities, office, restraint, fitness,
pool and an open motor courtyard. To serve residents and hotel visitors,
four levels of below grade parking are provided under the courtyard.
A 61-story (685 feet tall) reinforced concrete tower structure marks
the east side of the site. A one level basement, 16 feet deep, will
be constructed under the tower for mechanical and office usages
and the ground level will contain lobby, retail and service facilities.
There will be five stories of hotel amenity space such as a spa,
restaurant, meeting rooms, and ball room facilities. The next 19
stories will contain hotel room space with balconies. Mechanical
floors are provided at Levels 27 and 28 and above the penthouse
level. The tower columns are transferred at level 28 with a 6’-0”
thick slab to accommodate the building set back at the east and
west sides of level 29. Residential condominium space is provided
in the upper portion of the tower at level 29 through 59. Column
transfers at level 51, 52, 57, and 59 are supported by post-tensioned
concrete beams or thickened slabs. A Tuned Liquid Damper (TLD),
consisting of four reinforced concrete tanks with water, is located
at the top of the building to control building accelerations. The
Elysian Hotel and Private Residences is one of the first residential
buildings in the United States to integrate a TLD into the structural
design. Additionally, the superstructure will be clad with insulated
pre-cast concrete panels and metal panels. All designs were completed
in accordance to the Chicago Building Code.
Structural Systems Foundations
For this 700 foot tall tower, it was originally predicted that
foundations would extend to rock. However, working closely with
the geotechnical engineer, an aggressive scheme was devised to bear
at Chicago’s ‘hardpan’ clay later – located
approximately 85’ below the site’s grade – with
an allowable bearing capacity of 32 ksf. Belled drilled piers (or
belled ‘caissons’, as they are referred to in Chicago)
range in size from 2’-6” to 7’-0” with bell
sizes from 4’-0” to 20’-0”, using 8,000
psi concrete. The key was making sure total and differential settlements
were acceptable. And based on settlement predictions – this
system was determined to be feasible with special construction considerations
and settlement monitoring.

The center core shear walls are supported with a 12’-0”
thick mat foundation supported by a group of eight caissons with
7’-0” shafts and 20’-0” bells. The caissons
resist lateral base shears from the core shear walls. Reinforcing
for the mat consists of #11 top and bottom reinforcing bars and
#9 shear reinforcing bars. An 8,000 psi mix design was specified
for strength. Mega-columns, 6’-0” by 10’-6”
located at the north and south perimeter sides, are supported by
mega-grade beams 12’-0” wide by 16’-0” deep.
228-#11 reinforcing bars are provided for the bottom and 114-#11
for the top reinforcing. Shear reinforcing consisted of #7 bars
with 14 legs. An 8,000 psi concrete mix design was specified. Because
of the thickness of the mat and mega-grade beams, concerns for the
heat of hydration and maximum differential temperature between the
center of the members and their surfaces became apparent. To prevent
the potential for unwanted cracking, mass concrete provisions were
specified. These included the maximum temperature during the curing
process and maximum temperature gradient between the center of the
members and the surfaces. A self-consolidating, low heat of hydration
mix design was provided by the contractor to satisfy these provisions.
Thermal sensors were used to monitor the temperatures within the
members for a specified time period.

Four levels of parking are located at the west side of the site.
The lowest level is 47 feet below grade. Because of lateral earth
pressures at this depth, 30 inch thick reinforced concrete slurry
walls were designed with 4,000 psi concrete. The walls provide lateral
earth support for the below grade parking while also supporting
the gravity loads from the low rise steel building above. Under
the footprint of the tower on the east side, a one level basement
has 14 inch thick perimeter reinforced concrete walls to resist
lateral earth pressures and transfer lateral base shear from the
tower superstructure to the soil.

During construction, the temporary earth retention system for the
below grade parking structure consisted of four levels of internal
steel pipe bracing with wide flange whalers. These members braced
the concrete slurry walls until the permanent 10 inch two-way reinforced
concrete flat slabs were constructed at each level. The pipe bracing
spanned diagonally at the corners and 122 feet in the north-south
direction. Steel sheeting was installed at the tower basement perimeter
and large diameter pipes were used to brace the sheeting internally.
The bracing spanned 96 feet in the north-south direction. All the
temporary earth retention systems were designed by the contractor.
Floor Systems
At the four levels of below grade for parking, a 10” two-way
reinforced flat slab with drop panels will be utilized, with 6,000
psi concrete strength. Since the slab resists horizontal earth pressures
acting simultaneously with vertical gravity loads – a special
buckling analysis was done to insure the floors were sufficient
for this interaction.
For the typical tower floors - columns are located only at the
perimeter, which provides open floors between the perimeter and
center core walls. (This also directs the gravity load to the core
walls and perimeter columns engaged with outriggers – to help
these elements avoid uplift under wind loads.) The typical hotel
level floor plate is 97 feet in the north-south and 126 feet in
the east-west directions, while the typical condominium floor plate
is 86 feet in the first and 112 feet in the latter. An 8 inch two-way,
post-tensioned concrete flat plate supports typical residential
live loads. The slab spans 34 feet from perimeter to core wall and
50 feet between concrete outrigger walls. The concrete strength
is 5,000 psi. Slab deflections were limited to the span divided
by 360 for live loads, or the span divided by 240 for total long
term sustained loads after partitions are installed. Perimeter slab
deflections were limited to ½ inch or less where it supports
the precast building façade.
At the transition between hotel and residential at level 28 –
a 6’-0” two-way transfer slab at the east and west sides
transfers the 29-story residential perimeter columns above to the
offset hotel columns below. The slab is reinforced with #11 bars
top and bottom along with #9 shear reinforcing at the columns (where
required for punching shear resistance). For constructability purposes,
the transfer slab was poured in two separate sections. The first
was a 2’-0” thick bottom section followed by the remaining
4’-0” thick top section several days later. The first
2’-0” thick bottom portion was designed by the contractor
with post-tensioning to assist in supporting the wet weight of the
remaining 4’-0” thick pour section. Halvorson and Partners
(HP) designed the slab portions to behave compositely by adding
vertical shear reinforcing throughout the slab footprint to transfer
horizontal shear forces. The top of the slab was intentionally roughened
per ACI requirements to provide shear-friction between the two pours
and the concrete strength is 6,000 psi for both pours. HP also evaluated
the effects of the post-tensioning on the slab behavior for the
final condition where the composite slab sections together resist
the applied transfer column forces. Close communication and coordination
with the contractor was needed for the construction of level 28
to be successful.

Additionally, a full story deep beam is provided below level 7
to transfer two columns, each supporting 50 stories of load from
above. The 5’-8” wide by 19’-6” deep transfer
spans approximately 56’-0”. High strength concrete of
12,000 psi is provided and reinforcing consists of #11 top and bottom
bars with #7 shear reinforcing.
Gravity System
The
perimeter reinforced concrete columns and the interior core walls
comprise the gravity system by resisting the loads within their
tributary areas. All cladding will be supported directly by the
perimeter reinforced concrete columns and selected floor slabs.
Lateral System
The tower uses an efficient ‘core and outrigger’ lateral
system. However, as the tower grew from its original 40-story design
to its final 61-story configuration – there was no opportunity
to re-configure the structure or significantly increase structural
sizes. In order to make the structure work for the final height
– HP aggressively optimized the given structure for strength
and introduced a damping system to reduce accelerations due to wind
to meet standard criteria. See the next section for more.
The lateral load resisting system consists of an 18 inch thick
central reinforced concrete shear wall surrounding the core elements
and four reinforced concrete “mega-columns” located
on the north and south sides of the tower. The central shear wall
has outside to outside dimensions of 21’-6” in the north-south
and 56’-6” in the east-west directions. The mega-columns
are 6’-0” by 10’-6” at the base and transition
in size throughout the height of the building. Outrigger shear walls
in the north-south direction connect the core to the mega-columns.
These walls start at Level 7 and terminate at Level 40 on the south
side and Level 51 on the north side to create open spaces for the
top condominium units. The walls beginning at Level 7 allows for
flexibility in the space layout for the hotel functions. Reinforced
concrete link beams will be provided at the openings in the shear
walls. The widths of the link beams typically match the thickness
of the shear walls at the central building core. Link beams between
the core and the outrigger walls are typically wider than the walls.
Lateral forces are resisted by the Outrigger-Braced system in the
north-south direction and the central shear walls in the east-west
direction. The concrete strength for the mega-columns, core shear
walls, outrigger walls and link beams transitions from 12,000 psi
at the base to 8,000 psi to 6,000 psi to 5,000 psi at the top of
the building. Overall building drift is H/800 at the roof of the
building yielding a relatively stiff building.

Tuned Liquid Damper
As
described above, when the tower height increased significantly –
it became necessary to introduce a damping system to keep accelerations
due to wind within standard criteria, in lieu of major structural
revisions. Wind tunnel testing was conducted by the Boundary Layer
Wind Tunnel Laboratory at the University of Western Ontario (BLWT)
on this slender tower, with a height to width ratio greater than
7. As anticipated for its extended height, the structure’s
stiffness alone was insufficient to bring accelerations within acceptable
limits. With the assistance of the BLWT, HP studied options for
different combinations of structural stiffness and damping to develop
a cost effective structural solution that incorporates a Tuned Liquid
Damper (TLD) at the top of the building.
The TLD is the latest approach to controlling motion in tall, slender
building offering low cost, low maintenance and high performance
over a broad range of wind conditions. The Elysian is one of the
first residential towers in the United States to incorporate this
technology. Water-filled concrete tanks fitting within the central
core wall footprint will be located at the top of the building.
The movement of the water will be controlled with internal steel
baffles that produce a sloshing effect. The baffles are composed
of simple steel tube sections in a regular spacing. The water motion
works opposite the building motion to control accelerations produced
from wind forces. The Elysian’s TLDs will be tuned in two
directions to mitigate motion perception.
Photos courtesy of Halvorson and Partners.
|
 |

Case Studies:
Cultural Buildings
Educational Institutions
Green Buildings
Healthcare
Hospitality
ICF Buildings
Luxury Residential
Mixed Use
Office Buildings
Religious Structures
Tilt-Up Buildings
| Owner/Developer:
Elysian Development Group, LLC
Project Manager: Golub & Company
Architect: Lucien Lagrange Architects
General Contractor: McHugh Construction
Company
Structural Engineer: Halvorson and
Partners (HP)
Geotechnical Engineer: Ground Engineering
Consultants (GEC)
Wind Tunnel: Boundary Layer Wind Tunnel
Laboratory
at the University of Western Ontario (BLWT)
|
|
|