The Ritz Carlton Luxury Condominiums and Hotel
New York, NY
Buildings Home > Case
Studies: Mixed Use > The Ritz Carlton...
The
Ritz-Carlton Luxury Condominiums and Four Star Hotel is a 40-story mixed-use
building situated at the southern most tip of Manhattan. The property
has achieved a unique distinction in showcasing world-class architecture
at the gateway to Manhattan. This mixed-usedevelopment also has the distinct
honor of being the new home of the New York Skyscraper Museum. In addition,
the 40 stories, include three floors with public areas (restaurants, ballrooms,
meeting areas museum and mechanical level) ten floors with 298 hotel rooms
and
amenities and sixteen floors with 140 luxury condominiums.
The location of this structure posed many challenges for design
and construction. The proximity to the Hudson River and the required
depth of excavation necessitated a foundation and excavation retention
system capable of holding back as much as eighteen feet of water pressure.
The foundation walls and slabs also had to be designed to resist this
significant hydrostatic force. Wall thickness varied from 14 inches to
16 inches and a two-foot thick steel reinforced concrete slabs were used
to resist both upward and downward pressures between the pile caps.
To support the building loads at the base, while minimizing the extent
of excavation, dewatering and waterproofing, the pile design selected
was a 200-ton steel pipe filled with 10,000 PSI concrete. The weight of
the building required a total of 600 piles, which extended through forty-feet
of hydraulic fill to bear on solid bedrock.
The conditions of the soil below this irregular shaped structure required
that a dynamic response spectra analysis be conducted to accurately predict
the behavior of the structure during a seismic event. The design for seismic
loads also considered the high wind loading potential at this site. A
“coupled shear wall system” was elected to provide lateral
load resistance to the high winds of the New York Harbor with
a constant thickness of 12 inches. The added construction speed and convenience
provided by a constant thickness concrete
wall was achieved by deploying high strength concrete and varying the
strength from 5,000 psi to 10,000 psi.
Overturning resistance at the building foundations was accomplished using
a 7-foot thick reinforced concrete mat. The mat extended out to engage
the overturning resistance of heavily loaded gravity columns and the overturning
resistance of the piles. This system effectively formed a “Base
Outrigger” to minimize base rotations and eliminate the need for
rock anchors.
Cast in place concrete was selected as the material of choice because
its speed for this application. The two-day per floor construction
cycle perfected in New York allows the building to be constructed rapidly.
Flat plate construction minimizes the floor-to-floor heights while providing
a smooth ceiling surface requiring no additional framing for hotel rooms
and condominiums. The underside of the concrete is simply plastered. Flat
plate construction affords long open spans and cantilevered corners while
allowing for full flexibility in location of columns. This flexible arrangement
of columns is called a “shotgun pattern” and is not practical
with any other type of construction.
The gravity loads resisting system is a conventional reinforced flat-plate
slab supported by columns and walls. Spans in excess of 30 feet and corner
cantilevers extending as much as 14 feet in both directions necessitated
the use of a 9 inch slab. After a detailed finite element analysis of
the floor systems, the stresses and deflections were determined with higher
precision. Slab cambering was necessary to eliminate initial dead load
deflections in many of the long span areas. High strength concrete ranging
up to 10,000 psi was also utilized. The requirement of a column-free
ballroom space with a maximum ceiling height at the second floor was accomplished
by transferring an entire line of building columns. Due to the
depth restriction of 42 inches, “Post-Tensioned” transfer
girders were used. Each girder contains 120 “Monostrand” tendons
arranged in a draped profile. The tendons were tensioned, or “Jacked”,
in two stages in order to account for construction sequencing. Other conventionally
reinforced transfer girders as much as 10-feet deep were used to transfer
columns at other locations.
In addition to faster construction and excellent fire resistance, the
concrete framing systems provided this structure with inherent damping
benefits to resist movement due to high winds at the tip of Manhattan.
With the added stiffness, minimum vibration and sound transmission, concrete
buildings enjoy high levels of tenant comfort and are occupant friendly.
In this project and many others, cast in place concrete construction also
allows last minute
changes to be incorporated easily in the field with minimum or no interruption
to fast-track project schedules.
Construction Photos
|
 |

Case Studies:
Cultural Buildings
Educational Institutions
Green Buildings
Healthcare
Hospitality
ICF Buildings
Luxury Residential
Mixed Use
Office Buildings
Religious Structures
Tilt-Up Buildings
| Owner/Developer:
Millennium Partners
Architects:
Gary E. Handel
& Associates
Polshek Partnership
Architects
Structural Engineer:
DeSimone Consulting
Engineers
Concrete Subcontractor:
Laquilla-Pinnacle
|
|
|