Food
and Drug Administration (FDA) Headquarters
Montgomery, Maryland
Buildings Home > Case
Studies: Office Buildings > FDA CDER
Center for Drug Evaluation and Research (CDER)
The
Food and Drug Administration (FDA) currently employs over 6,000 people
in 40 buildings at 18 locations in the Washington, DC, metropolitan area.
Several years ago, FDA decided to consolidate their headquarters into
a single campus to improve operating efficiency and to develop state-of-the-art
laboratories, a central research facility, and offices that are flexible
enough to adapt to future changes. The completed campus will consist of
over 2 million square feet of space in 12 buildings constructed over an
eight-year period, with a projected construction cost on the order of
$900 million.
The project was awarded by the U.S. General Services Administration (GSA/National
Capitol Region) and is being designed and constructed under its Design
Excellence Program. The GSA Design Excellence Program, which is administered
by the Office of the Chief Architect, stresses creativity and is intended
to ensure top-quality design and construction for all GSA’s building
projects. The project utilizes land at the Naval Laboratory Campus at
White Oak, a base realignment and closure site, and includes reuse of
several existing historic buildings. GSA is managing the development process
for FDA, which will utilize 130 acres of the 670-acrebase, maintain existing
community facilities, and preserve environmentally sensitive areas.
The first phase of office construction is for the Center for Drug Evaluation
and Research (CDER), and consists of a 6-story building plus basement
encompassing more than 400,000 square feet. The facility houses offices,
conference space, storage, and other ancillary functions, and supports
adjacent testing and research facilities. The basement level incorporates
connections to an underground utility and materials distribution tunnel
system linking all campus facilities to a central utility plant and central
loading areas. The CDER office building project also includes two enclosed
pedestrian bridges that connect adjacent laboratory and office facilities.
The
CDER office building takes the plan form of a small letter “h”,
with four “bar” elements comprising the legs of the “h”-shaped
plan. Typical office functions are contained in these relatively narrow
“bar” elements, which are three bays in width. Building core
areas connect the office “bar” elements, and contain the usual
elevator, stair, restroom and mechanical shaft functions. The typical
bay size along a bar length is 29 feet 6 inches. Column spacing for the
3-bay-wide office areas is 26 feet 9 inches, 19 feet 8 inches, and 26
feet 9 inches; thus, total building width is 73 feet 2 inches.
All FDA buildings are designed to meet the requirements of GSA’s
P-100 document (i.e., Facilities Standards for the Public Building Service),
which serves as a supplement to basic IBC code requirements. Additionally,
all FDA campus facilities, including the CDER office building, are designed
to meet GSA’s Progressive Collapse Analysis and Design Guidelines,
which specify that the structure be designed to accommodate the removal
of any perimeter column at the first story without collapse of the remaining
structure. The guidelines prescribe special loading and demand-to-capacity
ratio criteria to be utilized for the analyses. These requirements led
to the creation of two independent computational models; one for standard
gravity and lateral design, and a second for progressive collapse design.
Final designs and rebar selection for individual concrete components are
a hybrid of the critical aspects of each design requirement.
The
monolithic nature of cast-in-place concrete construction provides inherent
benefits in terms of meeting progressive collapse criteria. Typical office
areas are constructed with 2-way flat slab construction, consisting of
8” slabs and 8” drop panels at columns. Core areas primarily
utilize one-way beam and slab construction. Relatively deep perimeter
spandrel beams support the exterior brick façade and provide the
necessary strength to accommodate GSA’s progressive collapse guidelines.
The standard column size is 24” x 24” for the full building
height. Building columns and foundation walls are supported by shallow
spread footings bearing on existing soils, though at one segment of the
facility, existing fill materials were improved and consolidated by deep
dynamic compaction methods. The rigid frame action of perimeter spandrel
frames, as well as the rigid frames created within core areas, will resist
lateral loads due to seismic forces.
Initial structural framing studies during the campus Master Plan phase
suggested that structural steel construction would be the most cost-effective.
However, budget concerns resulting from the final concept design cost
estimate led the design team to review a number of areas for potential
cost savings. It was determined that, with several key adjustments, a
cast-in-place concrete 2-way flat slab scheme would lead to substantial
cost savings. The adjustments included the addition of an interior column
line at the “bar” elements and a reduction in the floor-to-floor
height. The added column line would lead to efficient bay sizes favorable
to a 2-way system, and the interior column locations worked well within
the standardized office layout. With this modification, the 2-way slab
system was found to be slightly less expensive than structural steel framing,
and the reduction in floor-to-floor height led to significant savings
in exterior enclosure costs, as well as the costs of other interior vertical
construction components.
Concrete
framing provided the best framing solution for this project. The simple
characteristics of a 2-way flat slab system led to easier coordination
with architectural finishes and ceiling utility space requirements. Concrete
construction was also compatible with the building design’s unique
exterior architectural elements. For example, there are a number of tall,
nearly freestanding, stone-clad wall elements that connect sparingly to
the main structural frame. The monolithic nature of concrete construction
was well suited to address the multiple design challenges for these elements—robust
stiffness for resisting wind load, easy attachment of stone and brick
relief angles, and inherent rigidity and continuity needed to meet progressive
collapse requirements.
|
 |

Case Studies:
Cultural Buildings
Educational Institutions
Green Buildings
Healthcare
Hospitality
ICF Buildings
Luxury Residential
Mixed Use
Office Buildings
Religious Structures
Tilt-Up Buildings
Owner: General
Services Administration
Washington, DC
Architect: Kling in association with RTKL
Associates Inc.
Structural Engineer: Kling in association
with RTKL Associates Inc.
General Contractor: Centex Construction
Washington, DC
Concrete Contractor: Miller & Long
Washington, DC
Ready Mix Supplier: Superior Concrete
|
|
|