Pavements 
Home
 

Pavements  Overview 

Soil-Cement 

Roller- 
Compacted  Concrete
 

Concrete  Pavements 

Resources 

Tech 
Support
 

Stay Informed 

Find a Cement  Supplier 

Find Help 
Near You
 

Conferences 
and Training
 


RCC Recent Projects
Pavements Home > Roller-Compacted Concrete> Recent Projects > Fort Carson, Colo. Tank Hardstands

Tough Duty for RCC

The U.S. Army Corps of Engineers (USACE) have been specifying roller-compacted concrete (RCC) for both dams and paving applications for more than 25 years. USACE designed the first RCC dam in the United States—Willow Creek Dam in Heppner, Ore. which was completed in 1982. The USACE has also pioneered the use of RCC for heavy-duty paving applications at military bases throughout the U.S. Successful long-term performance of projects at Ft. Gordon, Ft. Lewis and Ft. Hood in the early ‘80s set the stage for additional work at Fort Bliss, Toole Army Depot, Fort Benning, Fort Campbell, Fort Drum, Fort Bragg and others.

Fort Carson, the army’s mountain post located outside Colorado Springs, Colo. is the latest military facility to utilize RCC pavements at its facilities. As part of an expansion program at the post, RCC is being used to pave the tank hardstands of several new maintenance facilities, as well as a 1.6 mile (2.6 km) tank trail. A total of approximately 70,000 cy (53,500 m3) of RCC will be placed at the facility.

Design Details

The pavement design for both the hardstand pavements and the tank trail consists of 10 in. (250 mm) thick RCC placed on 10 in. (250 mm) of granular base. Design flexural strength for all the RCC applications was 550 psi (3.8 MPa) at 28 days. To minimize random cracking, joints were sawed at 60 ft x 60 ft (18.3 m x 18.3 m) spacing.

The mix design per cubic yard (cubic meter) consisted of:

Cement (Type I/II) 383 lb (173.7 kg)
Coarse Aggregate
 

(ASTM C33; No. 7)
1565 lb (709.9 kg)
Mid-Size Aggregate
 
Crusher Fines
  522 lb (236.8 kg)
Fine Aggregate
   
(ASTM C33)
1391 lb (631.0 kg)
Water 220 lb (99.8 kg)


The original mix design included 25 percent of the total cementitious material to be Class F flyash for use as a mineral filler and to increase the minus No. 200 sieve size aggregate proportion of the mix. However, unfavorable early strength results as well as spalled joints during relief sawing operations caused the contractor to abandon its use on the project.

RCC Construction

Interstate Highway Construction, Inc. (IHC) of Englewood, Colo. began RCC placement in April 2008. The RCC was produced in a Rapidmix 400 pugmill set-up on site. Capacity of the plant was 400 tons/hr (363 metric tons/hr), although the actual production during construction varied from 200 to 250 tons/hr (181 to 227 metric tons/hr) due to work area availability, access and obstructions. Separate storage stockpiles were created for the three aggregate sizes. A front end loader transferred the aggregates from the stockpiles to a three bin cold feed blender where it was blended according to the mix design before being transferred by conveyor into the pugmill’s aggregate bin. The mixed RCC was hauled to the placing location using rear dump trucks.

Pugmill Producing RCC Placing RCC with High Density Paver
Pugmill Producing RCC at Fort Carson Placing RCC with High Density Paver at Fort Carson


At the placement site the trucks discharged the RCC into a Gomaco RTP transfer device which then was used to maintain a constant feed of material into the Ingersoll Rand Titan 8820 ABG paver. The high density paver was able achieve up to 92% of the specified required minimum compacted density of 98% of the modified Proctor density in accordance with ASTM D1557.

Initial and Final Compaction of RCC Placing Adjacent Lane of RCC
Initial and Final Compaction of RCC Tank Hardstands at Fort Carson
Placing Adjacent Lane of RCC at Fort Carson


Final compaction was achieved using a 10-ton (9.1-metric ton) dual drum vibratory roller, followed by a combination pneumatic roller and a 4 -ton (3.6 -metric ton) dual drum roller for surface sealing. Immediately following final compaction a concrete curing compound was applied to the surface to prevent premature surface drying.

To minimize the development of random cracking, joints were cut and sealed on a 60 ft x 60 ft (18.3 m x 18.3 m) joint pattern. The relief sawing was accomplished with a Soff-Cut early entry saw, allowing the cutting to be performed soon after final surface rolling. The sawed joints were then cleaned of any loose debris and filled with a silicone sealant.

Saw-Cut Joints Completed RCC Tank Hardstands at Fort Carson
Saw-Cut Joints on Completed RCC Tank Hardstands at Fort Carson Completed RCC Tank Hardstands at Fort Carson

Quality control testing consisted of in-place density tests using a nuclear moisture-density gauge. The maximum density and optimum moisture content were determined using the modified Proctor test method. The determined maximum dry density was 143 pcf (2290 kg/m3) and the optimum moisture content was 5.7 %. Testing results indicated that the specific minimum density of 98% of the modified Proctor test was easily achieved. RCC strength results from beams cast in the field met or exceeded the 550 psi (3.8 MPa) at 28-days strength requirement.

Credits:

Owner: U.S. Army Corps of Engineers
Designer: U.S. Army Corps of Engineers
General Contractor: Bryan Construction
RCC Contractor: Interstate Highway Construction, Inc. (IHC)

 

 

 

More about RCC:

Features & Benefits of RCC Pavements

Related RCC Links

Research in Progress

RCC FAQs

Paver-Compacted Concrete

RCC for Ports

Recent Projects

Find a RCC Contractor

 
Careers | Sitemap | Disclaimer | Privacy Policy | © 2009 Portland Cement Association - All Rights Reserved