CMS Recent Projects
Pavements Home >
Soil-Cement > Cement-Modified Soils>
Recent Projects
Cement Speeds Up, Stabilizes
TxDOT San Antonio Project
Story and photos by Jeff Hawk
Faced with a tight construction schedule and highly expansive soils,
Texas Department of Transportation engineers turned to cement to
speed up work and lower plasticity levels for a $7.5-million San
Antonio highway project. The Spur 66/Watson Road project, located
off SH 16, involves building a new 1.8-mile, four-lane state highway
spur feeding into a Toyota manufacturing plant currently under construction.
TxDOT is also administering a $15.8-million Bexar County contract
to widen Applewhite and Zarzamora, two county-owned roads that also
service the new facility. TxDOT officials were under the gun to
finish the projects prior to the plant’s slated opening in
early 2006. The projects’ designers opted for cement because
it offered “faster construction” than lime, says Larry
Coyle, assistant area engineer, TxDOT Bexar 410 Area Office.
Treating soils with cement is similar to lime-treating subgrade
except “you cut your time and work more than half,”
says Jim Stockbridge, project superintendent, Zachry Construction
Co, San Antonio. Zachry is the main contractor for the Spur 66 project.
Stockbridge says that processing and curing lime-treated material
requires five to seven days before placing the surface. In contrast,
cement modification of the subgrade soils takes only two days, says
Stockbridge.
“If you can eliminate the five days curing time and the second
mix [for lime], you’re able to get your asphalt crew or your
concrete crew in faster. Time is money,” says Stockbridge.
“With cement, you’re getting more done with less labor.”
Accustomed to working with lime, Zachry estimators projected that
production rates would run about 2,500 SY a day. Stockbridge says
cement is allowing him to double the amount of work his crews complete
on a daily basis. “We’re averaging 4,500 SY a day,”
he adds.
Lowering PI Levels
Before construction could begin, TxDOT had to address a problem
shared by all three roads: highly expansive subgrade soils. Tests
run on soil samples taken from the Spur 66 project site showed plasticity
levels in the high 30s in some areas. Plasticity index is a measure
of a soil’s tendency to expand and contract. PI levels greater
than 20 indicate highly expansive soils, which can shift under roadways
and cause premature failures.
TxDOT engineers had to find a stabilizer that would bring those
levels down before placing concrete and asphalt on top of the subgrade.
The San Antonio District Lab hired Raba-Kistner Consultants Inc.,
San Antonio, to evaluate how cement at different volumes affects
the plasticity in soil samples taken from the project site. Results
showed that an addition of only four percent of cement by volume
of dry weight of soil cut PI levels from 38 to 16. A seven percent
cement mixture dropped the PI levels below 10. Engineers decided
to specify 5.3% cement for the project. San Antonio-based Capitol
Cement supplied the cement.
The addition of cement is working well. Zachry crews are “getting
working platforms up pretty quick and able to maintain them, says
Colye. Cement has “done what we hoped it would do,”
he adds.
“The workability of it is excellent,” says Stockbridge.
“Cement will set up and give you a good working surface. Something
you can finish really tight.”
Cement has not only helped create a working platform out of expansive,
“black gumbo” soils, it has helped crews work through
a very rainy Spring. Wet weather turned untreated subgrade to mush,
stalling work, says Stockbridge. But in areas treated with cement,
Zachry crews were able to place asphalt “after a day or two
of drying,” says Stockbridge.
Cement modification permanently changes the characteristics of
the soil, making it more resistant to water, say cement industry
officials. The untreated soil on the site “really holds the
moisture and pumps,” says Stockbridge. After mixing the raw
subgrade with cement, “we haven’t had any problem with
pumping. It’s holding up our asphalt trucks and lay down machines
really good,” he adds.
Simple Construction
Another benefit realized with cement modification is the simplicity
of the process. “It’s not difficult at all,” says
Stockbridge, who has the process down to a near science. First,
crews work to bring the site down to the subgrade and level it out.
Three lanes measuring 38-ft by 388-ft are marked off.
Cement trucks equipped with a spreader bar then distribute 25 tons
of cement within each marked lane. Crews scarify and mix the cement
six inches deep and then peel it back to the original subgrade.
A motorgrader layers the cement-treated soil back in place in two-inch
lifts. Each lift is compacted with pneumatic and steel-wheeled vibratory
compactors. This not only ensures that the cement is well mixed,
it also helps Stockbridge meet density requirements. “We haven’t
had any density failures and we’re running close to 100% density,”
says Stockbridge.
After compaction, crews blade the area to final grade and cure.
Subcontractor Rammin Paving Co tops the cement-treated subgrade
with either asphalt and/or concrete pavement structure. Stockbridge
says he tries to place the surface immediately after finishing the
cement-treated subgrade because it seals in the moisture, allowing
the subgrade to cure underneath.
He adds that the process is well-suited for “fast-track’
projects like Spur 66. Says Stockbridge: “In this urban environment
that we’re all working in, you don’t have the luxury
of waiting seven days [for lime processing]. You need to be moving
traffic, so cement works out very well for us.”
For more information visit the Cement Council of Texas at www.RecyclingRoads.org
Pennsylvania Turnpike
The total reconstruction of the Pennsylvania Turnpike,
begun in 1999, signifies the first time that the toll road - known
as "America's First Superhighway" - has been replaced
from the ground up since it opened in October 1940. Part of this
massive reconstruction effort has been the stabilization of the
subgrade soils underneath the roadway using portland cement.
 |
Subgrade soils before cement modification. |
 |
Subgrade showing loose cement on subgrade. |
 |
Mixing the cement and subgrade soils together with water. |
 |
Close-up view of mixing tines. |
 |
Subgrade material after mixing with cement and water—called
"fluff." |
For a complete overview of the first section of this construction
project, please visit the following site: http://www.paturnpike.com/85to94/
|