Concrete  Technology  Home 

Cement  Basics 

Concrete Design  & Production 

Concrete  Construction 

PCA Research 

Durability 

Tech Support 

Stay Informed 

Resources 

CTT Newsletter 

FAQs  


Mass Concrete Case Study
Concrete Technology Home > Concrete Design and Production > Mass Concrete: Case Study

Mass Concrete: A Massive Beam in the San Francisco Bay
By John Gajda, PE, Principal Engineer, CTLGroup

The new San Francisco-Oakland Bay Bridge is one step closer to completion. American Bridge/Fluor, JV recently constructed the E2 Beam, which is one of three primary supporting members of the main suspension span of this landmark bridge.

Massive Beam
The E2 Beam will support the east portion of the self-anchored suspension span. The beam is 60½ m (200 ft) long, 6 m (20 ft) high, and up to 5½ m (18 ft) wide, and sits on two 33 m (110 ft) tall columns on a footing in the San Francisco Bay. The beam was constructed in a continuous 14 hour long concrete placement with 1,410 m3 (1,843 yd3) of 60 MPa (8700 psi) self-consolidating concrete (SCC). SCC was used because large quantity of closely spaced reinforcing steel and areas of high rebar congestion.

Formwork installation for the E2 Beam
Formwork installation for the E2 Beam in the foreground

Mass Concrete
Due to its dimensions, the beam was designated as mass concrete, where temperatures and temperature differences were to be controlled. Control was required from the time of placement until the hottest portion of the beam cooled back to near-ambient conditions. During this period, concrete temperatures were to be kept under 65°C (150°F) and thermal cracking was to be prevented.

While many specifications provide specific temperature difference limit (such as the often used generic limit of 20°C [35°F]), Caltrans did not specify a specific temperature difference limit for the project mass concrete. Instead, they specified that thermal cracking was to be prevented. Thermal cracking short circuits the benefits of the low permeability high performance concrete, which was specified to achieve the desired 150 year service life. Not specifying a definitive temperature difference limit allowed the necessary latitude to select an appropriate limit based on the properties of the concrete, and the requirement of that thermal cracking was to be prevented. In this case, CTLGroup developed an engineered temperature difference limit and tailored it to the properties of the project concrete.

Placement of the SCC concrete
Placement of the SCC concrete

Careful Planning
As part of the mass concrete designation, the project specifications required that a thermal control plan be developed to demonstrate how temperatures and temperature differences would be kept within the specified limits during placement and curing.

CTLGroup worked closely with American Bridge/Fluor staff to develop the thermal control plan based on detailed thermal modeling. Because of the high temperature rise of the concrete, the thermal control plan was developed based on having cooling pipes uniformly installed at about 700 mm (27 in.) on-center in the beam to remove internal heat during the curing and thermal control periods. The cooling pipes allowed the concrete to be placed with an initial temperature as high as about 25°C (75°F) without fear of exceeding the specified maximum temperature limit, and for thermal control to be completed in about 1½ weeks. Without cooling pipes, modeling showed that the initial concrete temperature would need to have been limited to about 10°C (50°F) and the time of thermal control would have continued for well over 1 month.

Manifolds and cooling pipe connections
Manifolds and cooling pipe connections. Due to the large number of pipes, supply lines were color-coded blue and return lines were color-coded red.

 

Conclusions
During the time of construction, temperatures were monitored on an hourly basis at numerous locations in the beam. The monitoring showed that temperatures and temperature differences were kept within the specified limits, and the temperatures and temperature differences were in reasonable agreement with the thermal modeling and thermal control plan. More importantly, after the formwork was removed, no thermal cracking was noted. Through careful and detailed planning, placement was a complete success.

Temperatures at some of the measured locations in the E2 Beam
Temperatures at some of the measured locations in the E2 Beam



The completed E2 Beam
The completed E2 Beam, with most of the formwork removed

 

John Gajda, PE,
Principal Engineer
CTLGroup, Skokie, Ill.
JGajda@ctlgroup.com

 


 

 
Careers | Sitemap | Disclaimer | Privacy Policy | © 2009 Portland Cement Association - All Rights Reserved