FDR_failed_asphaltDeteriorating roads are a constant problem for cities and counties. That is why engineers and public works officials are turning to a process called full-depth reclamation (FDR) with cement.

This process rebuilds worn out asphalt pavements by recycling the existing roadway. The old asphalt and base materials are pulverized, mixed with cement and water, and compacted to produce a strong, durable base for either an asphalt or concrete surface.

Full-depth reclamation uses the old asphalt and base material for the new road. There’s no need to haul in aggregate or haul out old material for disposal. Truck traffic is reduced, and there is little or no waste. View or download a fact sheet on FDR.

Recycling Saves Money and Natural Resources

Full-depth reclamation uses the materials from the deteriorated asphalt pavement, and, with the addition of cement, creates a new stabilized base.

A surface consisting of a thin bituminous chip seal, hot-mix asphalt, or concrete completes the road. The recycled base will be stronger, more uniform, and more moisture resistant than the original base, resulting in a long, low-maintenance life. And most important, recycling costs are normally at least 25 to 50 percent less than the removal and replacement of the old pavement.


Material Conservation: A Wise Choice

Conserving virgin construction materials through recycling with cement makes smart economic and strategic sense. A century of modern growth and urbanization in America has depleted once plentiful aggregate supplies. Frequently, aggregates either come from distant quarries at great expense or from local sources offering only marginal quality. Continuing to exhaust these valuable resources to rebuild existing roads only propagates and accelerates the problem. Additionally, if old asphalt and base materials are not recycled, they must be disposed of or stockpiled, increasing transportation costs and utilizing valuable landfill space. In some locales, old asphalt can no longer be landfilled. Environmental laws are becoming stricter, thus adding to the expense of mining new materials and landfilling old.
PCA is a member of the Asphalt Recycling and Reclamation Association (ARRA) and National Association of County Engineers (NACE).

ARRA LOGO rgb     NACELogo

Recycle, Rebuild

Recycling with cement makes the reconstruction of old roads a largely self-sustaining process. The original “investment” in virgin road materials becomes a one-time cost, which is renewed periodically, through cement stabilization and addition of a new, thin surface course.

Old Asphalt, New Foundation

Stabilizing the old asphalt surface, granular base, and underlying subgrade soil with cement creates a strong foundation for the pavement. Usually, there is little need for material to be removed or added. The old, brittle asphalt, when pulverized, becomes “black gravel” that will bond to hydrated cement readily. The removed material may be suitable for recycling into a new asphalt surface. In case the existing asphalt pavement does not meet the aggregate requirements for a good stabilized base, additional aggregates can be readily incorporated into the recycled aggregate during construction.

Design and Construction: Simple and Fast

The basic procedure is simple. The complete recycling process can be finished in one day, and local traffic can return almost immediately. The procedure includes the following steps:

Thickness Design

Pavement thickness can be determined by using the American Association of State Highway and Transportation Officials (AASHTO) Guide for Design of Pavement Structures.

Site Investigation

The site should be investigated to determine the cause of failure. Cores or test holes should be used to determine layer thicknesses and to obtain samples of the material to be recycled (which can include asphalt surface, base course aggregate, and subgrade).

Lab Evaluation

Material samples from the site should be pulverized in the lab to create an aggregate-soil mix that will be similar to that expected from the recycling process. The mix design procedure is the same as that performed for soil-cement. 

This includes the determination of maximum dry density and optimum moisture content. If unconfined compressive strength is used to determine cement content, a seven-day strength of 300 to 400 psi is recommended. 

How FDR Works 

Scarification and Pulverization

FDR_pulverizingDepending on the construction equipment available, and the thickness of the existing pavement, the roadway may need to be scarified (ripped) before it can be pulverized. Some equipment, however, is capable of pulverization without scarification first. Quality full-depth recycling is usually performed using equipment especially designed for this purpose. The depth of pulverization is usually six to 10 inches, which on secondary roads will typically include all of the surface and base, plus some part of the subgrade. To achieve the proper gradation after pulverization, more than one pass of the equipment may be necessary. The particle distribution should have 100 percent smaller than 2 inches and 55 percent passing a No. 4 (six-millimeter) sieve.


FDR_gradingThe pulverized material is shaped to the desired cross-section and grade. This could involve additional earthwork in order to widen the roadway. Final base elevation requirements may necessitate a small amount of material removal or addition.



Spreading Cement

Cement is spread in a measured amount on the surface of the shaped roadway, in either dry or slurry form.

Spreading dry cement
Lo res TXI slurry placement Dallas City street FDR, 12
Spreading cement (slurry)

Water Application


Water is added to bring the aggregate-soil mixture to optimum moisture content (water content at maximum dry density as determined by ASTM D558), either in front of the pulverizer/reclaimer or in the mixing chamber.


The aggregate-soil-cement-water mixture is combined and blended with the pulverizing/mixing machinery. Multiple passes of the mixer may be required to achieve a uniform blend of materials.


100_0006 copy

The mixture is compacted to the required density of at least 96 percent of standard Proctor density (ASTM D558). The compaction is usually performed with smooth-wheeled vibratory rollers. A pneumatic-tired roller may follow to finish the surface. Final compaction should take place no more than three hours past initial mixing of the cement. The field density and moisture are monitored for quality control purposes.



The surface is kept moist by periodically applying water to the surface, to make sure it does not become dry. This is done continuously through the curing period until the base can support traffic without deforming. The application of the prime coat should occur as soon as possible to ensure that moisture is sealed inside the base.

Pavement Surface

The new pavement surface consisting of a chip seal, hot-mix asphalt, or concrete is constructed to complete the recycling process.

Applying chip seal surface. 
011_8 copy
Applying hot mixed asphalt surface.

Quality Control

Recycling with cement follows the same basic procedures used for normal soil-cement operations. The success of a recycling project depends upon the careful attention to the following control factors:

  • Adequate pulverization
  • Proper cement content
  • Proper moisture content
  • Adequate density
  • Adequate curing

FDR Case Histories

Click here for FDR Case Histories.

For more information, see "The Road Recycled, Full-Depth Reclamation with Cement," Portland Cement Association, 2008.