| 2002 Concrete In Transit Awards Competition
Winners
Transit Home >
Transit Awards > 2002 Awards Competition
Winners

Winners of the second biennial Concrete in Transit
Awards program were recently selected by a panel of distinguished
judges consisting of Jim Rollings, Vice President of Parsons Transportation
Group, Glenn Zika, Vice President of the Chicago Transit Authority,
and Rob Kelly, Associate Architect of DLK Architecture. The competition
recognizes excellence in design and construction of transit projects
that best exemplify the use of concrete. Projects were judged on
the basis of creativity, transferability, aesthetics, economics,
and functionality.
Out of the entries submitted, the following four projects were
chosen as winners:
Millennium Line SkyTrain Extension
The
Millennium Line SkyTrain Extension is a 10-mile elevated precast
concrete segmental box girder aerial structure that adds to the
existing SkyTrain automated guideway system in Vancouver, British
Columbia, Canada.
Superstructure
The Millennium Line uses a single-cell, precast concrete segmental
box girder. The cross section of the segment was designed to be
torsionally stiff, allowing the construction of long spans through
curved sections of the alignment. Each guideway beam was typically
120 feet long, 7 feet deep, and consisted of twelve 25-ton concrete
segments.
About 6,000 concrete segments were cast at a special facility
constructed for the Millennium Line. The segments were stored at
the facility and moved to their erection sites using flatbed trucks.
Each segment was unique to fit the horizontal and vertical geometry
of the guideway rails in the section for which it was destined.
Each segment took one day to form and cast, using about 13 cubic
yards of concrete. The job was a massive undertaking, requiring
about 130,000 cubic yards of concrete. Even so, construction of
approximately 10 miles of standard elevated guideway was finished
in only 16 months.
Most
of the guideway, which is designed for a 100-year lifespan, was
built along existing rail and highway corridors and features an
unprecedented and unique application of truss-erected segmental
pre-cast guideway construction. Four of the massive 200-ton overhead
erection trusses, with lengths in excess of 325 feet, were used
to build the guideway. Standing on the guideway's support columns,
the launching girders raised pre-cast guideway segments into place.
Crews then threaded steel post-tensioning tendons through the concrete
segments to form, self-supporting beams wide enough to carry the
two SkyTrain tracks.
The inserts for rail fasteners were cast into the segments at
the plant and then the trackwork was laid directly on the structural
concrete. After the spans were erected, the elevations were surveyed,
the profile grade was adjusted, and shims were introduced beneath
fasteners as required. The average shim thickness for the entire
project was less than 1/4-inch. This is the first application of
direct fixation rail onto a segmental constructed guideway without
the use of plinths.
Substructure
More than 500 cast-in-place concrete columns support the Millennium
Line elevated guideway. The support columns are eight-sided and
either 5'-3" or 6'-10" wide (wider at SkyTrain stations and some
other locations). The columns flare out at the top to meet the inward
angle of the guideway segments placed above them. About 26 cubic
yards of concrete was required to build an average column. The foundations
that hold the columns were typically created using drilled pier
technology; steel casings with a diameter of 6'-6" were vibrated
into the ground, the earth was then augured from the center of the
casing, a reinforcing steel cage was lowered into the casing, and
concrete was then placed. In areas where it was appropriate, spread
footing foundations were used instead of drilled piers.
Unique Station Designs
The Millennium Line's 13 stations are key to the success of the
expanded rapid transit system. Each Millennium Line station is unique
and was designed by British Columbia's prominent architects and
structural engineers with input from an extensive public consultation
process. Designed to be futuristic while complementing the communities
in which they are located, the stations are built with provisions
for public amenities and security features to ensure that users
of all abilities and ages can use the line safely and efficiently.
Stations are all constructed primarily with concrete elements up
to the platform level. Columns and foundations are constructed with
cast-in-place concrete and the platforms are carried with precast
concrete beams. The station ancillary cores utilize architectural
concrete blocks.
The first section of the Millennium Line was turned over to the
operating authority in December of 2001 with the balance of the
line scheduled for completion by August of 2002, less than three
years after groundbreaking. The project is forecast to be completed
on budget and within the established construction schedule, and
once fully operational, the Millennium Line will have approximately
20 million riders annually by the year 2003. The total project cost
was $1.1 billion in Canadian dollars.
Project Credits
| Location |
|
Greater Vancouver, British Columbia, Canada |
| Owner |
|
RTP 2000 Ltd. |
| Engineer |
|
Earth Tech |
| Contractor |
|
SAR Transit JV |
| Concrete Supplier |
|
Lafarge Canada |
| Precaster |
|
SAR Transit JV |
Viaduct Restoration and Accessibility Project
The Viaduct Restoration and Accessibility Project includes the rehabilitation
of 20 concrete viaduct spans, the reconstruction of train platforms
to comply with ADA criteria, and construction of other accessibility
upgrades at the Paterson train station in Paterson, New Jersey.
Originally
constructed between 1924 and 1931 as part of Erie Railroad's grade
crossing elimination program, the project location includes 4 separate
bridge structures comprising a concrete viaduct that is 20 spans
long and measures 868 feet. The viaduct is characterized by classically
detailed concrete with four blank arches and a rectangular recess
on both sides of each span.
Concrete Design Criteria Since the four bridges spanning the Paterson
Viaduct are eligible for the National Register of Historic Places,
restoration of the Viaduct needed to follow the guidelines of the
New Jersey State Historic Preservation Office (NJSHPO); the concrete
mixes used in the restoration work had to replicate the existing
concrete, and be approved by the NJSHPO. To this effect NJ Transit
hired a conservator to take samples and analyze the concrete and
painted exposed steel. The conservator had also to analyze original
concrete samples to determine type and construction, develop replication
concrete mixes; produce a written report containing all findings
and concrete replication mixes; collect paint samples of existing
exposed steel; analyze original paint samples, develop replication
paint mixes, and produce a written report containing all findings
and paint replication mixes.
The report submitted by the conservator included concrete mixes
with recommended sands, fine aggregate, coarse aggregate, cements
and pigments along with a list of suppliers in the area. This report
was converted into a specification which became part of the contract
documents for bidding.
Platforms and Walkways
The station, owned and operated by NJ Transit, consists of a 1200
foot-long low level island platform on the viaduct. The island platform
serves two tracks: one track on either side of the platform. Project
work included the removal of the existing low-level island platform,
construction of a new high-level island platform, removal of the
existing canopy structure and its reinstallation onto the new high
level platform, and construction of an ADA complaint elevator from
street level to the new high level platform.
Consistent
with the NJ Transit Arts in Transit Program, some of the walkways
were designed and constructed following an artistic design with
the theme of "River Ribbons" which represents the Paterson's Great
Falls and the city's old nickname "Silk City."
The project was completed in September, 2001 and the total project
cost was $8 million.
Project Credits
| Location |
|
Paterson, New Jersey |
| Owner |
|
New Jersey Transit |
| Engineer |
|
New Jersey Transit |
| Contractor |
|
Railroad Construction Company, Inc. |
| Concrete Supplier |
|
County Concrete Corp. |
| Precaster |
|
Concrete Safety Systems |
Palm Desert Bus Shelter
The
Palm Desert Bus Shelter project included the design and construction
of a unique cast-in-place concrete bus shelter located adjacent
to the Buschlen Mowatt Galleries in Palm Desert, California.
Utilizing concrete to create the illusion of a mountain backdrop
gave the bus shelter an aesthetic appeal as part of a unique design
and provided an opportunity to maintain functionality and durability
throughout the project. It provided an opportunity to show riders,
residents, and guests that public transportation is something more
than a means to get to work.
Public Arts Program
Palm Desert, California was the first city within its county jurisdiction
to create a public art program. In 1986, the City Council adopted
an ordinance requiring developers to place art or pay a fee to the
Art in Public Places fund for each new structure they build. These
funds are used to purchase public art for placement throughout the
community. The goals of the Public Art Program in conjunction with
the City's Bus Shelter Improvement Program are to create an artistic
harmony between buildings, landscaping, art, and open spaces, as
well as to serve the people of the community by offering art as
a means for cultural expression and response.
With
the majestic Santa Rosa mountains as a natural backdrop, Buschlen
Mowatt Galleries recently opened its gallery of contemporary international
fine art in Palm Desert, California. In keeping with the City's
Art in Public Places motto, "A Museum Without Walls," developer
Tim Bartlett designed a fully functional bus shelter that complements
the dozen sculptures that adorn the exterior of the building. As
part of the City's Bus Shelter Improvement Program, the shelter
is owned by the City of Palm Desert, and maintained by the public
transit system, SunLine Transit Agency.
Design
Concrete was utilized for its functionality and durability, but
with a unique complementary twist - the concrete was incorporated
to create a mountain backdrop as an artistic enhancement while providing
protection from the desert's extreme climate, primarily its high
summer temperatures and winds. Concrete not only creates a design
concept that embellishes the architectural features adjoining the
fine art gallery but also incorporates passive protection from the
elements. The roof angle is designed to allow early morning, midday,
and afternoon sun to shine in the structure during the winter months,
while shading the midday and afternoon sun in the summer. The passive
resistance to temperature, wind and rain, combined with the easy
viewing of oncoming transit buses, and compartmentalized seating
enhances the overall transit experience.
The aesthetic aspect of the design was a primary concern in that
it had to carry the theme and material use of the overall development
from the art gallery through to the bus shelter. The art piece provides
the project continuity and art gallery appeal, while the mountain
backdrop, through the creative incorporation of concrete, provided
a blending with the building and material itself. The stained concrete
and stainless steel are nearly indestructible and are resistant
to graffiti. Daily maintenance is easily facilitated by the durability
of the building materials. The aesthetic and functional design alone
will increase the awareness, value, and appreciation of the public
transit system and its facilities to riders, guests, residents,
and other developers. The net result is increased ridership while
improving the public's concept of public transit.
The project was completed in May of 2001 and cost was $30,000.
Project Credits
| Location |
|
Palm Desert, California |
| Owner |
|
City of Palm Desert |
| Engineer |
|
Johnson & Neilsen |
| Architect |
|
Tim Bartlett |
| Contractor |
|
Hayhoe Construction |
| Concrete Supplier |
|
Hayhoe Concrete |
Renton Transportation Center
The
new Renton Transportation Center serves seventeen Metro and Sound
Transit routes and was constructed using distinctive flatwork patterns
for traffic-calming and delineation of transit zones from the public
zones located in Renton, Washington.
The project is a joint partnership between King County Metro Transit
and the City of Renton formed for the development of a new transit
center in the downtown Renton area. The new facility serves both
Metro and Sound Transit routes that provide transit service throughout
the greater King County region.
Project Highlights
Highlights of the new transit center include the use of craftsman-type
design elements that will help create an identifiable image in downtown
Renton. The project incorporates clear way-finding elements within
the "at grade" improvements. Colored concrete, as an example, identifies
the transit zone vs. the public or enterprise zone adjacent to storefront
activities. The score patterns also clearly identify the transit
shelters as a terminus or place of refuge for the rider.
The flatwork pattern at the primary intersection of the project
is smaller with a different texture, creating an obvious traffic-calming
feature to the area for pedestrian safety. A state-of-art crosswalk
system is also included for pedestrian comfort and safety. This
system features runway type lighting that is activated by infrared
sensors that prompt vehicle operators to see activity within the
crosswalks.
The
inviting color and patterns of the associated parking area doubles
as a plaza for gathering or events. Careful attention was given
to the transition between the parking and sidewalk grades in order
to create the feeling of a pedestrian plaza.
Provision of continuous covered walkways enhances the pedestrian
connections linking the transit users to Logan Street and areas
to the west of downtown. Also, the boulevard feel of Burnett and
its large canopy type trees create an intimate and inviting atmosphere
for the pedestrian. Coffee vendor and public restroom are provided
as customer amenities.
Completed in September of 2001, the combination of architecture,
revitalized pedestrian environment, and amenities and incorporation
of art and history will make the Renton Transit Center a bright
and positive contribution to downtown.
The total project cost was $3.8 million.
Project Credits
| Location |
|
Renton, Washington |
| Owner |
|
King County Metro / City of Renton |
| Engineer |
|
Parametrix, Inc. |
| Contractor |
|
Gary Merlino Construction Company |
| Concrete Supplier |
|
Stoneway Concrete |
Awards
Award presentations were made at the American Concrete Institute
Spring Conference in Detroit on April 21, 2002 and at the American
Public Transportation Association Commuter Rail/Rail Transit Conference
in Baltimore on June 10, 2002.
Enter your project into the next Concrete In Transit Awards competition.
Information
For more information, contact David Bilow by phone at 847.972.9064
or by e-mail at dbilow@cement.org.
|
 |

|