Transit 
Home
 

Transit 

Rail 

Structures 

Concrete Products 

Research 

Resources 

Transit Awards 

Tech Support 



Alameda Corridor Trench Project
Transit Home > Alameda Corridor

Freight traffic in operation - the completed project.

The Port of Los Angeles and Long Beach intermodal connection to the Los Angeles rail hubs predicted a doubling of the current 100 million metric tons of cargo now entering the ports each year. The new Alameda Corridor, which serves the ports, will initially handle 60 trains per day and have the potential to accommodate 100 trains per day when a third track is added in the future. Travel speeds in the new corridor are two times greater that when the line was situated at street level. This project demonstrated financial and contractual innovation as well as technical success. Most certainly, it serves as the model for others to follow.

The Alameda project consolidates four single-track routes into the port area as one. Previously, trains as long as 1.5 miles had to negotiate 200 street-level crossings and maximum speeds were barely 20 miles per hour.

During trench construction, a bypass track was constructed alongside the proposed trench to provide uninterrupted rail service. The trench is fitted with drainage troughs adjacent to the walls to handle precipitation. The design was based on a 50-year flood occurrence and incorporated pumping stations of 12,000 gallons per minute capacity at each end of the trench. The 51-foot-wide clearance between the trench walls was originally designed for two tracks and a service roadway. It was constructed, however, with three tracks to accommodate the expected increases in rail traffic. The 24-foot-6-inch overhead clearance allows railroad signals to be suspended from an overhead unistrut. Also, adequate clearance is provided in the event the line is electrified in the future.

Annual traffic volumes may exceed 150 mgt per year, thereby limiting the opportunity for track maintenance and requiring careful selection of track components. Special studies of the track section were initiated due to concern over early degradation of the ballast and the track components. These studies investigated optional materials and ballast depths under a stiff track modulus environment. The concrete trench floor slab supports trackwork that is laid on an 18-inch ballast bed with concrete ties spaced at 20 inches on center with 136-pound continuous welded rail on fasteners with rubber rail pads. Ideally, the track modulus should not exceed 10,000 psi. To achieve this, however, the design engineers considered adjustments to the pads, ballast depth, ballast material, and other components of the track structure. Studies to determine the actual track stiffness are ongoing. The results will undoubtedly benefit future trench projects.

Alameda designers chose several contiguous bored pile configurations based on the conditions of the site. Typically, 3-foot diameter piles spaced 4 feet apart were bored to a nominal depth of 14 feet below the proposed trench invert. The piles were cast in the drill hole leaving a 1-foot soil face between the piles. In some situations, 4-foot-diameter piles spaced 5 feet apart were constructed based on design loads. This type of wall construction was the predominant method on two-thirds of the 10-mile trench. The remaining one-third of the trench was composed of a secant pile wall due to high groundwater. Secant pile walls were spaced 0.8 to 0.9 pile diameters apart. Primary piles are secanted by secondary piles, thus providing a closed structure to act as a barrier where the groundwater table is high.

Placement of the sidewalls was performed in sections.

When the contiguous walls were completed on each side of the 51-foot-wide trench, the trench was partially excavated to 16 feet below grade to allow for construction of a heavily reinforced concrete cap beam. The cap beam essentially locks the piles together and was constructed to accept precast octagonal concrete struts that span the trench. The struts are spaced 25 feet on center. Following the installation of the struts, the trench was excavated to design depth. During excavation the deflection of the wall was monitored. A concrete bottom slab ranging from 1 to 4 feet thick was then cast in place. The variation in thickness was necessary to counteract hydrostatic uplift. Next, 6,000-psi shotcrete, 6 inches thick, was gunnited onto the pile wall and trowelled to provide a smooth face. The shotcrete was reinforced with welded wire fabric and attached to the piles with “L” dowels, previously set in drilled and epoxy-filled holes.

At intersecting cross streets spanning the trench, the piles were terminated approximately 24 feet below invert to achieve greater bearing capacity. Here, 14-inch precast slabs set on elastomeric pads were placed on cross girders to form a roadway bridge deck. A 5-inch-thick finished deck was then poured on the precast slabs.

Because the invert grade at the ends of the trench slope up to the ground surface, the use of struts across the trench was not possible. Therefore, cantilever walls were constructed at each end of the trench. In all cases, deflections were calculated not to exceed 1 inch.

Project Credits
Owner: Alameda Corridor Transportation Authority
Design-Build Team: Tutor-Saliba Corp., O&G Industries Inc., HNTB Design-Build Inc., and Parsons Transportation Group


 
Careers | Sitemap | Disclaimer | Privacy Policy | © 2010 Portland Cement Association - All Rights Reserved