Transit 
Home
 

Transit 

Rail 

Structures 

Concrete Products 

Research 

Resources 

Transit Awards 

Tech Support 



Don Valley Parkway/Canadian Pacific Rail Grade Separation
Toronto, Ontario
Transit Home > Don Valley Parkway

Tunnel jacking was used for the Don Valley Parkway grade-separation project.

When the Don Valley Parkway/Canadian Pacific (CP) Rail underpass was completed in 1990, it was the first project in North America to incorporate technology for jacking large structures under operating train traffic. Today, the underpass serves as part of a ramp to a busy highway. The reinforced concrete tunnel structure weighs 2200 tons (2000 tonnes), has an arch-like cross section 105 feet (32 m) long x 29.5 feet (9 m) high x 36 feet (11 m) wide, and was fabricated adjacent to two CP Rail mainline tracks—one of Canada’s most heavily traveled railway lines. The tunnel was then moved into its final position beneath the operating railway by a system of hydraulic jacks, in concert with mining operations carried out at the lead face of the structure.

The tunnel was cast in two longitudinal segments on a 3-foot (0.9-m) thick heavily reinforced concrete thrust base. The base slab’s weight counteracted the jacking forces as the tunnel moved forward. A mining shield provided on the structure’s lead face was designed for expected geotechnical conditions at the site.

The total jacking and mining operation was 92 feet (28 m) long. CP Rail maintained train traffic under slow orders, but without schedule interruptions during construction. Following each stroke of the 10,000-psi (69-MPa) hydraulic jacking system, workers carefully excavated within the structure and beneath the protective shield. Laser controls were used to maintain the structure’s alignment, which was skewed to the railroad embankment. Monitoring equipment recorded soil movements in the embankment ahead of the advancing structure and adjacent to an existing highway arch, as well as any settlement of the railroad tracks.

At the time of construction, the project involved a number of unique features: it was the largest such structure to be moved by jacking and mining, the first arch structure to be built in this manner, and the first skewed structure to be so moved. The project demonstrated that tunnel-jacking methodology is compatible with North American construction techniques and can be a cost-effective system for the construction of grade separations beneath heavily traveled railways, highways, or even airport runways.

Project Credits
Owner: Municipality of Metropolitan Toronto, ON
Consultant: Delcan Corporation, Toronto, ON
Subconsultant: Cementation Projects, Ltd., London, UK
Geotechnical Consultant: Golder Associates, Toronto, ON
Contractor: Matthews Contracting Inc., London, ON


 
Careers | Sitemap | Disclaimer | Privacy Policy | © 2008 Portland Cement Association - All Rights Reserved