Transit 
Home
 

Transit 

Rail 

Structures 

Concrete Products 

Research 

Resources 

Transit Awards 

Tech Support 



Waterfront Transit Line Bridge over Conrail Freight
Cleveland, Ohio
Transit Home > Waterfront Transit Line Bridge

The Waterfront Transit Line was the first extension of Cleveland’s rail transit system in 25 years. The 2.2-mile (3.5-km) line’s opening on July 10, 1996, was scheduled to precede the Cleveland Bicentennial on July 22. The rail line was intended to “reintroduce” the city to its waterfront. The Waterfront Transit Line Bridge is Ohio’s first precast concrete segmental bridge.

The only bridge structure on the Waterfront Transit Line is 645-feet (197-m) long with five continuous spans and carries two transit tracks. It clears operating freight tracks of the Consolidated Rail Corporation by almost 24 feet (7.3 m) and is about 15 feet (4.6 m) above a city street. Restrictions on allowable vertical gradients for a light-rail transit vehicle, combined with these clearance requirements, dictated the configuration of the superstructure: a single-cell concrete box girder. Maintaining freight train operations and meeting the date of the Bicentennial celebration dictated the type of construction: precast segmental.

Construction for the fast-track project began in September 1994. Precasting began in February and was completed by the end of April 1995. Girder erection started in early April 1995. This overlap necessitated the close scheduling of required segments to meet the critical erection schedule. The total construction period was 22 months.

The 70 box girder segments were cast about 100 miles (161 km) south of Cleveland at a vacant heavy assembly plant. Casting beds held two segments to allow continuous match casting. Segments were trucked to the construction site as needed, because of a lack of site storage.

Precast segments were placed alternately on each side of a cast-in-place pier segment according to the balanced cantilever method. Precast segment installation time was a mere 15 to 20 minutes—enough time between freight train movements to avoid interference. A continuous concrete plinth was cast in place on the box girder deck for attachment (direct fixation) of the rails to the structure.

Precast segmental concrete construction allowed quick fabrication, minimum site impact, fast erection, and ease of construction. The fast-track schedule was too aggressive to ensure enough time for steel girder fabrication and delivery.

The choice of precast segmental concrete construction for the Waterfront Transit Line proved to be the optimal solution, given constraints on time, cost, and construction.

Project Credits
Owner & Engineer: Greater Cleveland Regional Transit Authority, Cleveland, OH
Architect: Parson, Brinckerhoff, Quade & Douglas, Inc.
Contractor & Precaster: Kokosing Construction, Inc., Columbus, OH


 
Careers | Sitemap | Disclaimer | Privacy Policy | © 2010 Portland Cement Association - All Rights Reserved