Transit 
Home
 

Transit 

Rail 

Structures 

Concrete Products 

Research 

Resources 

Transit Awards 

Tech Support 



Whittier Access Project
Whittier, Alaska
Transit Home > Whittier Access Project

Interior of the Whittier Tunnel showing the roadway pavement and track rails.

During the military buildup of World War II, the U.S. Army Corps of Engineers built a railroad spur to Whittier, Alaska, a port town on Prince William Sound. The 15-mile (24 km) track connected Whittier to the mainline of the Alaska Railroad, which serves the state’s major population centers. After World War II, Whittier and the surrounding Chugach National Forest began to attract recreationists and tourists, and access was only by boat, plane, or train. The Whittier Access Project has now changed that, however, by connecting Whittier with Alaska’s highway system.

The Tunnel Segment Conversion Project, part of the larger project, called for an innovative reconstruction of the 2.5-mile (4.0-km) long railroad tunnel, creating the longest highway-rail crossing in the world. The dual-use facility allows alternating one-way automobile traffic, but also gives Alaska Railroad trains the right-of-way. Drivers arrive at a toll plaza and staging area at one of the tunnels and travel through single-file one way at a time.

The tunnel flooring system provides for dual use by automobile/truck traffic and train traffic. The flooring system consists of 8-foot (2.4-m) wide x 7.5-foot (2.3-m) long x 14-inch (360-mm) thick precast concrete grade crossing modules—Startrack II—placed end to end for a total of 14,000 ft (4270 m). The modules are designed to support both railroad and highway loads, with the rails set in a premolded trough that allows the top of the rails to be flush with the top of the pavement for smooth driving and safety. Once the rails were installed, the troughs were filled, forming flangeways for train wheels. The shoulders remaining on both sides of the precast modules were then filled with cast-in-place concrete, creating a 115-foot (3.5-m) wide driving lane.

Installation of the modules occurred during extended work windows of 4 to 6 days. There is also a complex tunnel ventilation system to accommodate normal and emergency operations, and a traffic control system to maximize the traffic carrying capacity for both trains and vehicles. The $32-million tunnel project was constructed using the design/build process to meet the overall project’s fast-track schedule.

Project Credits
Owner: Alaska Department of Transportation and Public Facilities, Juneau, AK
Owner’s Representative: HDR Inc., Anchorage, AK
Design/Build Contractor: Kiewit Pacific, Anchorage, AK
Crossing Manufacturer: Oldcastle/Utility Vault Co., Fontana, CA


 
Careers | Sitemap | Disclaimer | Privacy Policy | © 2008 Portland Cement Association - All Rights Reserved