Slurry Walls for Groundwater Control
Waste Treatment Home
> Overview > Slurry Walls for Groundwater
Control
Slurry Walls Used to Manage Waste
A
slurry wall is a non-structural underground wall that can serve
as a barrier to the horizontal flow of groundwater. A slurry is
a watery mixture of insoluble matter. Cement-based slurry walls
are self hardening mixtures that may include clay, soil, and slag
cement in addition to portland cement. Slurry walls are constructed
by placing the mixture into a trench excavated to the desired depth.
The cement-based slurry remains to set up and form a permanent underground
cut-off wall to control groundwater movement.
Slurry walls are used in waste management to control
the flow of groundwater at contaminated sites. One of the earliest
uses of slurry walls in EPA’s Superfund program was at Brodhead
Creek in Stroudsburg, Pennsylvania. The 12-acre (4.9 ha) site is
the location of a former coal gasification plant. In 1981, EPA took
steps to stop the seepage of coal tar from the site into the creek
by constructing an underground cement-bentonite slurry wall. The
slurry wall was installed between the toxic coal tar deposits and
the creek. The 12-inch (30mm) wide, 638-foot (194-m) long trenched
wall ranged in depth from 18 to 23 feet (5.5-7m).
Although some coal tar as source material of contamination
was pumped from the site, EPA determined that complete removal of
the residual coal tar would be technically unworkable due to site-specific
constraints. Both the first 5-year review (1999) and second 5-year
review (2004) of the remedy completed by EPA indicated that the
remedy including the slurry wall continues to be protective of human
health and the environment. More.
Use of Cement-Bentonite
Slurry Wall in the Closure of an Oil Refinery Sludge Basin
Work
was completed in early 1992 to close a 5.5 acre (2.2ha) stormwater
sludge basin for an oil refinery company. The basin, which had served
as a stormwater collection and settling pond for over 40 years,
contained oily sludge with concentrations of hazardous constituents
including metals and organic compounds. The closure plan included
two portland cement applications; (a) installation of a cement-bentonite
slurry wall and jet grouting to contain the site and (b) solidification/stabilization
treatment of the basin’s contents.
The most important properties of slurry walls are low permeability
and compatibility with site conditions including groundwater. Both
soil-bentonite (SB) and cement-bentonite (CB) slurry mix designs
were tested. Testing indicated that both material mix designs SB
and CB were compatible with the site’s groundwater. Permeability
tests were performed on both SB and CB trial mixtures using the
site’s groundwater as the leachate. In general the CB mix
produced an initial permeability on 1X10-6cm/sec which
gradually decreased as the CB continued to cure. Soil-bentonite
trial mixes generally produced permeabilities in the range of 1X10-7cm/sec
but held steady for the three pore volume duration of the test.
Both mix designs were determined to be acceptable. The SB mix design
required considerable more material handling, mixing and clean-up
compared to a CB mix design.
Cement-bentonite was selected for its acceptable permeability at
initial installation and demonstrated decrease in permeability during
extended cure, compatibility with site groundwater, and cost.
The basin’s closure plan design included installation of
the CB slurry wall and jet grouted wall down to a depth of 40 to
45 feet (12-14 m) into underlying clay. The underlying clay was
approximately 70 feet (21 m) thick.
The
slurry wall was installed by trenching by backhoe, filling the trench
with the CB slurry as trenching progressed. Jet grouting involving
jetting a mixture of cement, bentonite, and native soils between
two parallel rows of steel sheet piling along a narrow portion of
the property. The sheet piling and jet grouting were also keyed
into the underlying clay layer of the site.
At the end of the project the basin’s contents were surrounded
by a low permeability wall keyed into the low permeability clay
beneath the site. Other work for the closure included cement-based
solidification/stabilization of the basin’s contents and installation
of a cover and cap system.
The closure is monitored. No issues involving the closure have
been reported by the State regulator.
More information:
Cement-Bentonite
Slurry Trench Cutoff Walls (IS227)
"Remediation
of Oil Refinery Sludge Basin" (PDF)
"RCA
Closure of Refinery Sludge Basin" (PDF) from the Proceedings
of the Fourth Great Lakes Geotechnical/Geoenvironmental Conference
on in-Situ Remediation of Contaminated Sites, Editor: Reddy,
K.R., University of Illinois at Chicago, May 1996".
Advantages of Cement-Bentonite
(CB) Slurry Trench Methods Over Soil-Bentonite (SB) Trench Methods
- The CB method is not dependent on the availability or the quality
of soil for backfill.
- The CB method is more suitable in trenching through weak soils
where trench stability may be a concern. The CB slurry has a higher
density than SB slurry and begins to set within hours after excavation,
thereby reducing the chance of failure.
- The CB slurry sets up to a stiff claylike consistency. Trenches
may be cut through the wall without sloughing. Construction traffic
may cross the trench after a few days.
- The construction sequence is more flexible. The CB method permits
trench construction in sections to meet site constraints. It adapts
to hilly surfaces where a step-type construction can be performed.
With the SB method, the long open trench necessary to accommodate
the flat slope of the backfill normally requires trenching continuously
in one direction at a constant elevation.
- With a CB slurry trench, construction may proceed during subfreezing
temperatures. With the SB method, special precautions are required
to keep the backfill from freezing.
- The width of a CB trench is generally less than for a SB trench.
For the SB method, the trench must be wide enough to permit free
flow of the backfill material.
- With the CB method an area adjacent to the trench is not required
for mixing, making it more suitable on projects with space limitations
such as the crest of a dam. Also, cleanup is easier with the CB
method.
More information on slurry wall applications, design, construction
methods and specification can be found in PCA’s publication
Cement-Bentonite
Slurry Trench Cutoff Walls, IS227.
FAQ: What low-permeability
ranges are possible with cement-bentonite slurry walls?
Permeability is one of the most important factors
in the design of a slurry wall. Both laboratory and field tests
indicate that the permeability of cement-bentonite slurry walls
range from 1X10-6 cm/sec to 1X10-7 cm/sec.
Compatibility with site conditions is also very important. Permeability
tests should be run with the subject site’s groundwater or
leachate.
|