Water Resources 
Home
 

Water Resources  Overview 

Soil-Cement 

Roller- Compacted  Concrete 

RCC Database 

Resources 

Find a Cement  Supplier 

Find a Contractor 

Stay Informed 


Roller-Compacted Concrete Projects
Water Resources Home > Roller Compacted Concrete > Recent Projects >Big Cherry Dam


New RCC Dam Replaces 70-Year Old Concrete Dam

Geoffrey L. Cowan, P.E., Dewberry & Davis LLC, Keith A. Ferguson, P.E., Kleinfelder, Inc., and Fares Y. Abdo, P.E., Portland Cement Association


New spillway operating for the first time in April 2006
The Old Big Cherry Dam is a 43-ft (1 3.1-m) high, 225-ft (68.6-m) long cyclopean concrete dam located in Wise County, Virginia near the Virginia/Kentucky state line. The dam impounds Big Cherry Reservoir, the water supply for the Town of Big Stone Gap, Va. The dam which was constructed in 1935, has been classified as a high hazard impoundment by the Virginia Department of Conservation and Recreation (VDCR). Dewberry & Davis LLC (Dewberry) has performed numerous engineering studies of the dam and reservoir during the past 20 years, including dam safety inspections, stability analyses, dam break studies, water supply, and rehabilitation studies. Past studies have determined that the old dam would be unstable during passage of the Probable Maximum Flood (PMF), the required spillway design flood. In addition, the Corps of Engineer's Phase I inspection report found the spillway capacity to be 20 percent of the required full PMF. Because failure during the PMF could result in loss of life, the dam had been operating under a conditional operation and maintenance certificate from VDCR since the inception of the Virginia Dam Safety Program.

Big Cherry Reservoir provides water supply to the town of Big Stone Gap water treatment plant. During dry spells, such as the summers of 1999 and 2002, reservoir levels have fallen to dangerously low levels prompting the Town to institute conservation measures and to examine alternatives for increasing the Town's water supply. Water supplies in neighboring Norton and throughout the region are also routinely stressed during dry periods, which points to a regional water supply problem.


Before constructing the new roller-compacted concrete (RCC) dam, the 4 million gallons (15.1 million liters) per day capacity water treatment plant produced an average water supply of approximately 1.7 MGD (6.4 MLD) which was very near the safe yield of the old reservoir. The water treatment plant will be able to safely treat over 3 MGD (11 MLD) with the new dam and increased reservoir storage in place.

Preliminary engineering studies were performed by the engineering team of Dewberry and GEI Consultants in which the following options for both stabilizing the old dam and increasing reservoir storage were evaluated:

  • Installation of post-tensioned anchors to stabilize the dam during passage of the PMF

  • Construction of an RCC dam overtop of the old concrete dam

  • Construction of a new RCC dam just downstream of the old dam and submerging the old dam
Big Cherry dams soon after construction of the new dam.

It was determined that construction of a new RCC dam downstream of the old dam and raising the permanent lake elevation 7 ft (2.1 m) to increase water supply was the preferred alternative to stabilizing and raising the existing dam. The New Big Cherry Dam helps reduce the region's water supply problem and the Town has negotiated agreements to sell treated water to neighboring municipalities once the increased supply becomes available.

 

For more information about the design and construction of the dam, highlighting the RCC mix design, cost, and core test results, click here to download a PDF of the full case study.

 


More on RCC:
Estimating RCC Costs for Dams
Performance of RCC
Recent Projects
FAQs
RCC Database
RCC/Soil Cement Contractor Directory