Water Resources 
Home
 

Water Resources  Overview 

Soil-Cement 

Roller- Compacted  Concrete 

RCC Database 

Resources 

Find a Cement  Supplier 

Find a Contractor 

Stay Informed 


RCC Frequently Asked Questions
Water Resources Home > Roller Compacted Concrete > FAQs


Click on question for answer.

Q: Could RCC dams be founded on non-rock foundation?

Q: What are the different types of facing systems used for RCC dams?

Q. What is the difference between Roller-Compacted Concrete (RCC) and Soil Cement (SC)?

Q: What are the control and required densities for RCC?

Q: What values of coefficient of roughness “n” are typically used in the Manning’s formula when designing open channels and spillways with soil-cement (SC) or roller-compacted concrete (RCC)?

Q: What methods are available for edge compaction of RCC?

Q: How are RCC mixtures for water resource applications proportioned using the soils spproach?

Q: Should RCC lifts be bonded?

Roller-compacted concrete (RCC) is a no slump concrete that must be dry enough to support the weight of large vibratory compaction rollers yet wet enough to permit adequate distribution of paste. RCC dams are typically constructed in 1-ft (0.3-m) lifts and, because of the dry nature of the mix, subsequent lifts placed after the initial set time of previous placed lifts do not necessarily bond without the introduction of bedding mortar or conventional concrete. The material within each lift is referred to as “parent” RCC and the horizontal joints between layers are referred to as lift joints. Bonding of lift joints is important for two reasons; structural stability and seepage control.

Structural designs of gravity dams must address structural stability in terms of overturning, sliding, and internal stresses. Consequently, when considering internal stresses, both the strength properties of the parent RCC and lift joints must be evaluated. In most cases, the lift joint is weaker than the parent RCC except where bedding mortar or bedding conventional concrete is utilized across the entire lift surfaces. Proper bonding of RCC lifts could result in lift joint strength equal to or greater than the strength of the parent RCC.

Although seepage normally is not a structural concern, excessive seepage may produce excessive internal uplift pressure not accounted for in the design, permit the loss of large amounts of water, create a maintenance problem involving collection and disposal, cause internal erosion of the structure, or create freeze-thaw problems at the downstream face. Seepage along horizontal lift joints should be distinguished from other sources of seepage such as through the parent RCC, control joints, cracks and foundation drains. Bedding mortar/concrete will reduce permeability at the lift joints but would not have a significant effect on the seepage from other sources.

When an RCC lift is covered with the next lift before the preceding lift reaches initial set, the joint at the interface is considered a fresh joint and should provide a strong watertight joint for reasonably workable RCC mixes. If the lower lift reaches initial set prior to covering with another lift, a cold joint begins to develop, resulting in loss of bond strength and potential increase in permeability. Generally a cold joint occurs in non-retarded RCC within 4 to 6 hours and within as little as 1-1/2 hours when ambient temperatures are at or above 90 degrees F. Once a cold joint develops, a bedding layer treatment may be needed to achieve the required bond strength as well as water tightness. Contaminated surfaces should always be cleaned prior to placement of subsequent lift regardless of the joint maturity. Also some projects require placement of bedding mortar for a specified width along the upstream face at all horizontal lift joints to limit seepage at these joints.

Spreading bedding mortar.Bedding mixtures generally have consisted of either bedding mortar or bedding concrete with bedding mortar being more common due to its greater ease in manually spreading across the lift surface. Bedding mortars typically contain sand; a cementitious content ranging from 400 to 600 pcy (235 to 355 kg/m3); water; water reducer; and set retarder. The bedding mortar typically has a slump ranging from 7 to 9 in. (180 to 230 mm) with a minimum set time of 3 hours at 95 degrees F (35 degrees C). The primary difference between bedding mortar and concrete is that bedding concrete contains a small percentage of coarse aggregate and the concrete has a slump range from 5 to 7 in. (125 to 180 mm).

Back to top.

Q: What are the control and required densities for RCC?

A: Compressive strength and density test results from numerous roller-compacted concrete (RCC) projects were analyzed and the data indicated that the density has a direct effect on the strength of RCC. Sufficient density of a good RCC mix can be achieved if proper compaction means and methods are implemented.

The required density of RCC is often referred to as specified minimum density and is typically defined in the project specifications. Prior to production placement of RCC, a control (or reference) density is established. At least four different approaches have been used to determine the control density. These are:

  1. Soil compaction techniques

  2. Laboratory tests to determine the density of compacted specimens using a vibratory table or hammers

  3. Calculation of theoretical air-free density

  4. Proof rolling of test lift(s) to determine the maximum achievable density

Once a control density is established, the required minimum density can be calculated based on the project specifications. Typically, engineers specify the required minimum wet density to be 96 to 98 percent of the wet control density. Calibrated nuclear density gauges are used to determine the density of RCC in the field. Based on the field test results, engineers can determine if the achieved density meets the density requirements of the project.

Detailed information on density of RCC and descriptions of test methods are described in PCA’s publications, Roller-Compacted Concrete Density: Principles and Practices ( IS541) and Guide for Developing RCC Specifications and Commentary (EB214).

Back to top.


More on RCC:
Estimating RCC Costs for Dams
Performance of RCC
Recent Projects
FAQs
RCC Database
RCC/Soil Cement Contractor Directory

 
Careers | Sitemap | Disclaimer | Privacy Policy | © 2010 Portland Cement Association - All Rights Reserved