Water Resources 
Home
 

Water Resources  Overview 

Soil-Cement 

Roller- Compacted  Concrete 

RCC Database 

Resources 

Find a Cement  Supplier 

Find a Contractor 

Stay Informed 


Roller-Compacted Concrete Projects
Water Resources Home > Roller Compacted Concrete > Recent Projects - McKinney Lake Dam


An RCC First in North Carolina

The first dam remediation project in North Carolina to use roller compacted concrete (RCC) for overtopping protection.

The first dam remediation project in North Carolina to use roller compacted concrete (RCC) for overtopping protection, the McKinney Lake Dam is located on Hitchcock Creek, north of Rockingham, North Carolina. Situated upstream of the McKinney Lake National Fish Hatchery, the dam’s primary purpose is to supply water to the facility.

Originally constructed in the late 1930s as a Works Progress Administration project, the 23-ft-high (7 m) dam consists of an earthfill embankment with a concrete corewall. The principal spillway is located in the middle third of the dam and consists of a concrete gravity overflow section and a rectangular concrete outlet channel. An unlined emergency spillway was cut into the left third of the embankment.

When state officials determined that the dam suffered from safety deficiencies, roller-compacted concrete (RCC) was chosen as the material of choice for improvements. Plans called for increasing spillway capacity and raising the top of the dam.

Remediated Structural Features
Maximum height of embankment 23 feet (7m)
Elevation of embankment crest 284.9 feet (86.8 m) MSL
Overall length of dam 718 feet (219 m)
Control crest width of principal spillway 40 feet (12 m)
Control crest elevation of principal spillway 277.5 feet (84.6 m) MSL
Upstream slope of embankment 2H:1V
Downstream slope of embankment 3H:1V
Crest width of emergency spillway 240 feet (73 m)
Crest elevation of emergency spillway 280.0 feet (85.3 m) MSL

The project’s design concept addressed inadequate spillway capacity by armoring a section of the embankment with RCC, and raising the crest of the embankment to contain the 1/3 PMP flood level plus freeboard. The armored section of the embankment serves as the emergency spillway.

 

The RCC mix design was as follows:

Type I/II portland cement 450 lb/yd3 (267 kg/m3)
Modified NCDOT roadbase aggregate (1-1/2 MSA) 3,428 lb/yd3 (2034 kg/m3)
Water 262 lb/yd3 (156 kg/m3)

The specified 28-day compressive strength was 3,000 psi (20.7 MPa). The unusually high cement content was required to compensate for poor grading of the sand fraction of the NCDOT base course aggregate. In addition the silt fines were on the high side of the specified range (3% to 8% by weight) for minus #200 (75 micron) sieve material.

The 1600 yd3 (1223 m3) of RCC armoring was placed on the upper portion of the upstream slope, the crest, the downstream slope, and an apron area beyond the downstream slope. Sheet piling driven along the edges of the RCC serves as spillway training walls to contain the design discharge. The training walls converge to direct outflows up to the projected 100-year flood level through an existing box culvert under the downstream access road. The end result:< improvements with RCC increased the spillway discharge capacity to more than 11,000 cfs (311 cms), or about 47 cfs per foot (4.3 cms/m) of weir length—a substantial improvement over the dam’s original capacity.

Project Team

URS Corporation, Denver, Colorado designed the dam improvements and is the engineer of record.

Schnabel Engineering Associates, Greensboro, North Carolina, was the project manager responsible for owner and dam safety coordination, as well as construction oversight. Schnabel’s Charlotte office performed field and laboratory testing.

Atlas Resource Management, Fayetteville, North Carolina, was the general contractor.

Gears, Inc., Crested Butte, Colorado, was the subcontractor for RCC mixing and placement.

S&ME, Louisville, Tennessee, performed the RCC mix design.

Click here for a printed version of this case study.


More on RCC:
Estimating RCC Costs for Dams
Performance of RCC
Recent Projects
FAQs
RCC Database
RCC/Soil Cement Contractor Directory