Water Resources 
Home
 

Water Resources  Overview 

Soil-Cement 

Roller- Compacted  Concrete 

RCC Database 

Resources 

Find a Cement  Supplier 

Find a Contractor 

Stay Informed 


Roller-Compacted Concrete Projects
Water Resources Home > Roller Compacted Concrete > Recent Projects >Yellow River Watershed Dams 15 and 16


RCC Makes Two More Georgia Embankment Dams Safer

Building on the success of roller-compacted concrete (RCC) overtopping protection at Yellow River Watershed Dams No. 14 and No. 17, the Natural Resources Conservation Service (NRCS) and Gwinnett County, Georgia recently completed upgrades to two more embankment dams. The dams are located approximately 30 miles (48 km) northeast of Atlanta. NRCS built the dams in early 1960s; however, Gwinnett County currently owns and operates the dams.

The county has been experiencing fast growth over the past two decades. Earthen embankments which were originally built to protect rural pasture and farmland are now protecting residential and commercial developments. A major issue with many of these earthen dams has been inadequate spillway capacity. Due to their lack of spillway capacity, these dams have been re-classified as hazardous dams and required upgrades to prevent catastrophic failures during maximum design flood events. Since the mid-1980’s, RCC has been successfully used on more than 100 earthen dams to armor the downstream slopes and the crests of dams, thereby allowing overtopping of the dams without the risk of failures due to erosion of embankment materials.

The two recently completed dam overtopping protection projects, Yellow River Watershed Dams No. 15 and No. 16, are within 3 miles (5.4 km) of each other. Golder Associates, Inc., Atlanta, designed No. 15 upgrades and Schnabel Engineering, Atlanta, designed No. 16 upgrades. NRCS and Gwinnett County elected to award both projects under one contract to realize the cost savings from setting up one instead of two RCC plants. The contract was awarded to ASI Constructors of Buena Vista, Colorado. Based on bid quantities, a total of 12,500 yd3 (9,600 m3) and 3,000 yd3 (2,300 m3) of RCC were used for No. 15 and No. 16, respectively. The average in-place unit cost of RCC considering the bids for both sites was $157.34/yd3 ($205.78/m3).

Yellow River Watershed Dam No. 16 Yellow River Watershed Dam No. 16 covered
Yellow River Watershed Dam No. 16 Yellow River Watershed Dam No. 16 covered with soil and grassed.

The RCC plant staging area was adjacent to No. 15 dam site. Dump trucks transported the RCC from the mixing plant to the hoppers of telescoping cranes positioned at the dam sites. The cranes then conveyed the materials to the points of placements. The projects were completed in March 2007. For aesthetical purposes, the RCC slopes were covered with soil and grassed.

Yellow River Watershed Dam No. 15 Yellow River Watershed Dam No. 15 covered
Yellow River Watershed Dam No. 15 Yellow River Watershed Dam No. 15 covered with soil and grassed.


More on RCC:
Estimating RCC Costs for Dams
Performance of RCC
Recent Projects
FAQs
RCC Database
RCC/Soil Cement Contractor Directory

 
Careers | Sitemap | Disclaimer | Privacy Policy | © 2009 Portland Cement Association - All Rights Reserved