Water Resources 
Home
 

Water Resources  Overview 

Soil-Cement 

Roller- Compacted  Concrete 

RCC Database 

Resources 

Find a Cement  Supplier 

Find a Contractor 

Stay Informed 


Soil-Cement Case Study
Water Resources Home > Soil Cement > Moss Creek Dam


Large Soil-Cement Drop Structure Solves Major Erosion Problem
John L. Rutledge, P.E., Vice President
Freese and Nochols, Inc.

The Moss Creek Dam is located on Moss Creek east of Big Spring, Texas. It is owned by the City of Big Spring, but operated by the Colorado River Municipal Water District, as part of their water supply system for the west Texas area. In April of 2000, a four to eight inch (100 to 200 mm) rainfall fell over a 26 square mile (67 sq. km) drainage area in less than 6 hours. The runoff was later equated to approximately the 25-yr flood.

The primary spillway for the dam consists of a 350-foot (1 07-m) wide uncontrolled concrete weir in the left abutment that provides for an 11-foot (3.3-m) drop. The channel that directs the flow back to the original channel has a steep, 3% grade for its 1,500-foot (457-m) length. Prior to this event, the spillway had operated only once in the 25 years since its construction and suffered only minor erosion damage. In 2000, however, the erosion damage was dramatic, with gullies as deep as 25 feet (7.6 m) formed in the channel. An asphalt access road was also destroyed. The eroded material was deposited downstream, blocking much of the channel and causing the floodwaters to back up within 2 feet (0.6 m) of the District's pumps. Though much of the exit channel was severely damaged, the embankment and the spillway structure were not threatened during the event. However, it was clear that major repairs would be needed to avoid future risks to the spillway.

View of drop structure and exit channel.
Several alternatives were reviewed in the initial analysis. The final recommendation was to construct a large soil-cement drop structure that would be located and shaped to minimize the required excavation. It was designed as an oval bowl with a narrow exit channel, forcing higher tailwater to properly contain the hydraulic jump within the uniquely shaped basin. The configuration of the oval bowl shaped structure focused lower flows through the central portion of the basin and allowed higher flows to drop into the basin from the sides. The final maximum height of the basin was designed as an average 35-foot (10.7-m) drop. The long exit channel was partially lined with additional soil-cement and included two small soil-cement drop structures to effect better grade control and more appropriate flow velocities.

The plan for the soil-cement placement called for one-foot (0.3-m) steps with approximate 45 degree compacted faces on all of the slopes of the drop structure bowl. This configuration balanced the desired dissipation of some of the flow energy with the need to simplify construction techniques and lower costs by avoiding formed steps. In the exit channel, soil-cement was plated on the bottom and on the slopes in order to hold down the construction quantities. Subsurface drainage was provided by two long, horizontal drains installed along the face of the slope underneath the soil cement with downstream outlets located beyond the expected hydraulic jump area.

Construction for the project began in early November 2001. Excavation for both the stilling basin bowl and the exit channel and the simultaneous construction of a new embankment adjacent to portions of the exit channel continued through December and into early January of 2002. During this time, a mix design for the soil-cement was prepared using the contractor's proposed aggregate. The specifications provided for a minimum 1,500 psi (10.4 MPa) compressive strength with wet-dry and freeze-thaw tests showing less than 10% loss. Based on the laboratory results, a design of 8% cement was used. This provided average laboratory strength of about 2,000 psi (13.8 MPa) with minimal losses from the two durability tests.

Placing soil-cement for drop structure and exit channel.
Soil-cement placement began in March 2002 in the downstream channel. Placement and spreading was performed by a dozer or motor grader, when possible. Compaction then followed with a vibratory roller. The specifications called for average 98% of maximum standard Proctor density and field density results during construction averaged about 100%. The downstream channel and the stilling basin floor were completed in March and placement of the stilling basin bowl steps began in early April 2002. Placement procedures included the placement of soil cement material into a spreader box with a front-end loader. The 12-in. (300-mm) lifts were then compacted using a vibratory roller. A motor grader was used to form the 1:1 step faces. The 1:1 outside faces were then compacted using a rubber tire attached at an angle to the motor grader blade. Compacted densities of the step face were consistent with the remainder of each step and met the required density. Soil-cement placement was completed in early May. Slightly less than 10,000 cubic yards (7,645 m3) were placed in about a month.

Laboratory strengths for the soil cement were generally about 2,000 psi (13.8 MPa) at 28 days compared to the specified minimum strength of 1,500 psi (10.4 MPa). Cores taken during construction verified the needed strength with field strengths ranging from about 1,700 to 2,200 psi (11.7 to 15.2 MPa) after more than 28 days.

The contractor, Price Construction of Big Spring, performed the construction at a cost of $914,000. The cost of the soil-cement in place was $45.76 per cubic yard ($59.85/3) for 9,900 cubic yards (7,569 m3) placed. The new drop structure and exit channel for the spillway have been in place for more than three years and appear to be in excellent shape, though the spillway has not operated during that time.



More on Soil Cement:
Overview
Embankment Slope Protection
Bank Protection/Levees
Drop and Grade Control Structures
Liners
FAQs
Southern California Case Study
Moss Creek Dam Case Study
Rueter-Hess Dam and Reservoir Case Study
RCC/Soil Cement Contractor Directory

 
Careers | Sitemap | Disclaimer | Privacy Policy | © 2010 Portland Cement Association - All Rights Reserved