Water Resources 
Home
 

Water Resources  Overview 

Soil-Cement 

Roller- Compacted  Concrete 

RCC Database 

Resources 

Find a Cement  Supplier 

Find a Contractor 

Stay Informed 


Soil-Cement Frequently Asked Questions
Water Resources Home > Soil-Cement > FAQs > Determining thickness of soil-cement for upstream slope protection

Q: How is the thickness of soil-cement for upstream slope protection of embankments determined?

A: Typical thickness design of soil-cement slope protection depends on the severity of the intended application and on the method of construction. Soil-cement can be placed for slope protection in horizontal lifts adjacent to the slope (stair-step) or parallel to the slope (plating). PCA guidelines for the stair-step and plating methods of construction are summarized below.

Stair-Step Construction Method

Stari-step slope protection at Jackson Lake Dam, Colo.Soil-cement for embankment slopes exposed to moderate-to-severe wave action or high velocity lateral flows should be constructed using stair-step method of construction. To determine the minimum thickness required, designers should consider the density of the proposed soil-cement and all possible loading conditions, including but not limited to uplift due to wave action and hydrostatic pressures that may develop during rapid drawdown. The thickness would then be determined to insure that the soil-cement weight is heavy enough to resist all upward forces. In determining the soil-cement thickness, designers should also include a safety factor in the form of an additional sacrificial amount of soil-cement to account for wear or loss of surface materials, which can occur especially if the lift edges are unformed or not compacted to a high density or the structure is exposed to severe freeze-thaw action. Based on the performance of soil-cement bank protection projects over the past 50 years, the majority of any surface wear and material loss will occur within the first couple years of service.


On many projects, the required thickness based on structural analysis would be less then the thickness dictated by the embankment slope, lift thickness, and construction equipment. Stair-step construction on most projects has been accomplished by equipment approximately 8 feet wide placing soil-cement lifts 8 to 9 feet (2.4 - 2.7 m) wide, 6 to 12 inches (150 - 300 mm) thick. For slopes, ranging from 2H:1V to 4H:1V, the resulting thickness of soil-cement measured perpendicular to the slope would be between 2 and 2.5 feet (0.6 - 0.8 m). (Figure 1). This thickness compares favorably to a typical rock riprap with bedding design. If desired, the overall thickness can be reduced by placing narrower widths. On some projects, conveyor belt or other placement methods were used to reduce the lift width to 6-ft. (1.8 m) or less.

Plating Construction Method

Plated soil-cement slope protection at Upper Duck Detention Basin in Clark County, Nev.Plating method of construction can be used on slopes 3H:1V or flatter on projects not exposed to severe applications. Although this method has been used on a few projects where the slopes were as steep as 2.5H:1V, it is generally not recommended for this steep a slope because of the difficulty in placement and compaction. The steeper slope requires the use of lighter compaction equipment or additional cable supported equipment working from the crest to maintain stability of the vibratory roller.

Similar to the structural requirements for stair-step construction, the required thickness for plating method is typically determined based on structural analysis considering all possible loading conditions and accounting for possible loss of surface materials during the desired service life of the structure. The analysis should include but not be limited to hydrostatic pressure uplift due to rapid drawdown and wave action.

Graph showing relationship of slope, facing thickness, layer thickness, and Horizontal layer width.
Figure 1. Relationship of slope, facing thickness, layer thickness, and Horizontal layer width.

For detailed information on soil-cement design and construction methods, refer to PCA publication EB203, Soil-Cement Guide for Water Resources Applications.


More on Soil Cement:
Overview
Embankment Slope Protection
Bank Protection/Levees
Drop and Grade Control Structures
Liners
FAQs
Southern California Case Study
Moss Creek Dam Case Study
Rueter-Hess Dam and Reservoir Case Study
RCC/Soil Cement Contractor Directory

 
Careers | Sitemap | Disclaimer | Privacy Policy | © 2010 Portland Cement Association - All Rights Reserved