|
| Airports
Pavements Home > Concrete Pavements > Airports
Paving of airport runways, taxiways, and aprons has provided a strong market
for portland cement concrete in recent years, as commercial and military airports upgrade their ground facilities to keep up with increasing air traffic. In 1992,
25 million flights took off or landed at the nation's 100 largest airports. By 2005, the Federal Aviation Administration projects that number to increase by almost 38% to 34.5 million. Demand for concrete is greatest at these large facilities, because concrete provides the substantial pavement strength required to withstand the impact of airplanes such as the 747, which can weigh more than 850,000
lb (382,000 kg.) when fully loaded.
Some 1.1 million metric tons of portland cement were used in the United States
for airport pavement projects in 1995, up 22% from a decade earlier,
when 895,000 metric tons were used. Since there has been little demand
for construction of new airports in the United States for some timethe
Denver International Airport being a notable exceptionmost of
this cement is going into concrete needed for existing airport pavements
or adding new runways to existing airports. Engineers and contractors
are taking advantage of fast-track technology to upgrade ground facilities
with minimal traffic disruption, and continue to hone design techniques
to achieve maximum pavement life.
The first United States airport runway was built in 1928 in Dearborn,
Michigan, by the Ford Motor Company for a Ford-manufactured plane
called the Silver Goose. This and other early runways used variable
pavement thicknesses similar to those of early highways: concrete
8 or 9 in. (20 or 22.5 cm) deep at the edges and 6 or 7 in. (15 or
17.5 cm) thick at the center. Until World War II, engineers designed
these concrete pavements based on the anticipated loads imposed by
refueling trucks carrying gasoline to the airplanes, rather than the
airplanes themselves, because the trucks imposed a more critical wheel
load. Concrete pavement markets span from driveways and parking lots
to mainline interstate highways.
In 1942, at the beginning of World War II, 93 million sq yd (74
million sq m) of airfield pavement was placed in the United States
as the country mobilized to get planes airborne. At that time, 6 in.
(15 cm) deep concrete pavements were the norm, but heavier airplanes
created the need to increase concrete runway pavement depth to 12
in. (30 cm) thick. Eventually, engineers specified runway pavements
as thick as 24 in. (60 cm) to accommodate heavy loads imposed by larger
aircraft. The addition of more wheels to these airplanes, which better
distributed the loads on the pavement, reduced the pavement depth
required to 12 in. (30 cm) in the late 1940s.
Today, specifications for airport concrete pavement vary depending
on subgrade conditions, expected loading, and anticipated pavement
life-span. New concrete runways at non-hub airports generally range
in thickness from 9 to 12 in. (22.5 to 30 cm), while runways at hub
airports often are constructed 15 to 18 in. (37.5 to 45 cm) thick
to withstand larger and more frequent loading.
Durability an Issue In an effort to create
more cost-effective, longer lasting airport pavements, the Federal
Aviation Administration continues to investigate the durability of
alternative pavement designs. One such study is underway in Illinois
at the Greater Rockford Airport, where researchers are examining a
taxiway paved under three different specifications. Because pavements
usually deteriorate first at their joints, investigators are studying
a section of unjointed, 1,200 ft (360 m) long concrete made with shrinkage
compensating cement (Type K) that expands during the concrete's early
curing to counteract the expected shrinkage that causes cracking.
In addition, the unjointed pavement includes steel reinforcing fibers
and is reinforced with prestressed steel to improve its tensile strength.
The pavement section is only 7 in. (17.5 cm) thick.
Researchers will compare this unjointed pavement with a 10 in.(25
cm) thick pavement section that also contains Type K cement and steel
reinforcing fibers, but no prestressed steel reinforcing. Contractors
placed this pavement with joints spaced from 85 to 200 ft (25.5 to
60 m) apart. The third pavement section is a control section, consisting
of conventional, 15 in. (37.5 cm) thick concrete pavement containing
joints spaced 20 ft (6 m) apart. Paving engineers expect results of
the study to influence future airport pavement design. Engineers anticipate
at least 40 years of service—twice the number of service years
airport pavements are usually designed to meet—from pavements
constructed at the $4.2 billion Denver International Airport, opened
in early 1995 after 5-1/2 years of construction. Contractors placed
2.5 million cu yd of concrete to create five 12,000 ft (3,600 m) long
runways, plus taxiways and aprons. To ensure pavement durability,
designers carefully compensated for Denver's expansive soil, which
tends to swell and move, by excavating the site. Contractors then
laid down 6 ft (1.8 m) of compacted, non-expansive soil; a 12 in.
(30 cm) deep subgrade layer of rototilled, lime-treated soil; and
an 8 in. (20 cm) thick cement-treated base before pouring 17 in. (42.5
cm) of concrete paving.
At many airports today, fast-track technology plays an important
role in the rehabilitation of existing pavements because airport officials
cannot close runways and taxiways without severely impacting operations.
At the Seattle-Tacoma International Airport in Washington, for example,
engineers created a complex slab replacement schedule for a 1994 rehabilitation
project that allowed contractors to rebuild the runway at night and
reopen it to airplane traffic each morning. Contractors demolished
two pavement slabs each night and replaced them with temporary, precast
panels. Each subsequent night, the temporary panels were removed,
and new slabs of high-early-strength concrete were cast in place.
At the same time, workers demolished two additional existing slabs
and replaced them with the temporary precast panels. In this manner,
contractors replaced 73 concrete runway slabs with minimal disruption.
|