Transit 
Home
 

Transit 

Rail 

Structures 

Concrete Products 

Research 

Resources 

Transit Awards 

Tech Support 



Getty Center Tram Guideway
Los Angeles, California
Transit Home > Getty Center

The Getty Center Tram system transports visitors from an underground parking structure to the J. Paul Getty Museum located on a hilltop. The Tram vehicle is cable driven and supported by an air cushion. The total guideway length is 3540 feet (1080 m), with the aerial portion at 2625 feet (800 m) and an average span length of 210 feet (64 m). The guideway is single lane, with a double-lane, off-center bypass section.

The superstructure configuration was chosen by the project’s owner, architect, and contractor from three alternative cross sections considered during preliminary design, based on cost, aesthetics, and constructability factors. The chosen section consists of two L-shaped precast, prestressed concrete web beams spanning from column to column with a cast-in-place connecting slab forming a U-beam section. Web beams were designed to support the simple-span applied loads. Spans were later post tensioned in the field into four- to six-span continuous units. A 4-inch (100-mm) thick flying surface was cast on top of the completed U-beam section. The air-cushioned vehicle runs on the flying surface.

AutoCAD software was used to develop each precast element in its spatial geometry and then rotate the piece into its geometry in the forms. Precast web beam construction permitted casting over 10,000 inserts directly into the concrete to a tolerance of 1/8 inch (3 mm).

At some locations the guideway is supported on columns over 43 feet (13 m) high. At other locations the guideway superstructure is supported directly on drilled pier caps without columns.

Precast concrete crossheads were used to speed site construction of these heavily reinforced pier elements. Grouted sleeve connections were used to fasten crossheads to columns. Large steel bar lugs were used to secure the superstructure to the substructure and to resist lateral and vertical seismic forces. Precast web beams were erected within one to two days after crosshead erection and grouting.

The J. Paul Getty Trust built a world-class art facility at this site and thus demanded the highest quality in design and construction of the transportation facilities. Concrete was the material of choice for the Tram Guideway to solve the complex structural design and close geometric tolerances; to provide a warm, clean, and maintenance-free structure; and to contribute to the ride quality and passenger comfort of the Tram. The combined use of precast and cast-in-place, pretensioned and post-tensioned concrete made construction along the preferred alignment feasible and cost effective.

Project Credits
Owner: The J. Paul Getty Trust, Santa Monica, CA
Architect: R. Meier & Partners Architects, Los Angeles, CA
Engineer: BERGER/ABAM Engineers, Inc., Federal Way, WA
Contractors:
Project: Dinwiddie Construction Co., Los Angeles, CA
System: Otis Transit Systems, Farmington, CT
Guideway: A.T. Curd Constructors, Inc., Glendale, CA
Precaster: The Niobrara River Company, Rialto, CA


 
Careers | Sitemap | Disclaimer | Privacy Policy | © 2009 Portland Cement Association - All Rights Reserved