Hickory Log Creek RCC Dam and Reservoir Will
Supply Much Needed Water
Randall P. Bass, P.E., Schnabel Engineering
Charles M. Kahler, P.E., Schnabel Engineering
 |
| Almost completed Hickory Log Creek RCC Dam |
The Cobb County-Marietta Water Authority (CCMWA) and the City of Canton,
Ga., recognized the need and started the planning process for a new
water supply reservoir more than ten years ago. The resulting roller-compacted
concrete (RCC) dam to create the reservoir is being completed at the
same time the area is experiencing the worst drought on record.
Hickory Log Creek Dam is a 180-ft (55-m) high, 956-ft (291-m) long
RCC gravity dam. The dam will impound a 411-acre (166-hectare) reservoir
with a supply capacity of 44 mgd (167 mld). A pump station located
approximately 1.5 miles (2.4 km) below the dam on the Etowah River
will provide water for initial filling and will supplement the reservoir
to maintain the desired supply capacity.
Early planning studies identified that both an earthen dam and
an RCC dam were potential viable options for the site. Because the
type of dam would not affect the yield, the selection was based
on economics and schedule. After considering all the various factors,
it was determined that the RCC dam would cost about $4 million less
and can be completed within the City’s ambitious schedule
to complete construction by end of October 2007.
Planning and Design Parameters
Since the accelerated project schedule would not allow for completion
of the entire design and approval by Georgia Safe Dams Program prior
to start of construction, the project was separated into two phases.
Phase I design and construction work covered foundation excavation
and treatment, infrastructure improvements, and erosion and sediment
controls. Additionally, Phase I foundation work served as an extension
of the geotechnical/geological field exploration program. To overcome
the fact that portions of the dam’s footprint area were inaccessible
due to steep rock slopes, the team decided to continue the subsurface
investigation work after the foundation was exposed and access was
more affordable. Phase II work covered building the RCC dam and
reinforced concrete training walls and ogee crest spillway. This
phase design work progressed while Phase I construction was underway.
The project design storm was the probable maximum precipitation
(PMP), which over the 8.2 square mile (21.2 square km) drainage
basin produced an inflow of nearly 64,000 cfs (181 m3/sec.) during
a hypothetical 6-hour storm. Due to property constraints, only 10
ft (3 m) was available above the normal pool to top-of-dam. To pass
the design storm safely through the spillway with a maximum head
of 10 ft (3 m), a 250-ft (76-m) long spillway with ogee crest was
designed. A 110-ft (33.5-m) long gated spillway section was designed
in the center of the spillway width that included a 6-ft (1.8-m)
high Obermeyer Crest Gate. When the crest gate is fully lowered,
this spillway section has the capacity to pass 16 ft (4.9 m) of
reservoir head.
Because the dam site contained a very narrow valley with steep
abutments, a 250-ft (76-m) long spillway crest transitioning to
a 130-ft (39.6-m) wide stilling basin was designed. Design calculations
and a hydraulic model study performed at the Utah Water Research
Laboratory at Utah State University in Logan, confirmed that this
configuration would safely pass the design storm.
Construction
The low-bid for the first phase contract was $5.1 million and was
awarded to Thalle Construction Company in October 2005. The Phase
I Contract consisted of the foundation excavation, abutment preparation,
temporary stream diversion, site access roads and the primary staging
area, and concrete cutoff wall construction and grouting program.
The contractor completed the mass excavation by late February 2006
and began selective blasting of the rock foundation in early March.
Blasting operations were completed by July.
Nicholson Construction Company, as a subcontractor to Thalle Construction
Company, performed the grouting program between late June and mid-October
2006. This consisted of a double row grout curtain with primary
holes located at 20 ft (6.1 m) on centers. The depth of the grout
curtain was generally 25 ft (7.6 m) in the floodplain area and 35
to 80 ft (10.7 to 24.4 m) within the abutment areas. A drainage/inspection
gallery was designed within the dam with the center of the gallery
located 18 ft (5.5 m) downstream of the dam baseline (front face
of the dam) and extending up the majority of the abutment face.
The very ends of the abutment sections were founded on partially
weathered rock (PWR) containing numerous seams of fine-grained material
that would limit the installation of a grout curtain in this area.
A 20-ft (6.1-m) deep concrete cutoff wall was constructed through
the PWR at each abutment end.
At $36.6 million, Thalle was also the low bidder on the second
phase of the project. Subsequently, Thalle teamed with ASI Constructors,
Inc. as a subcontractor to construct the dam.
The main section of the dam was built using RCC. Geomembrane-lined
panels, anchored to the vertical upstream face achieved the dam’s
waterproofing. Capri provided the liner. The downstream face of
the dam was constructed with conventional concrete within the spillway
area and grout enriched RCC elsewhere. The slope of the downstream
face is 0.8H:1V.
The conventional concrete steps within the spillway section were
built concurrently with the dam RCC lifts. However, the spillway
training walls were constructed afterwards using self-consolidated
concrete. The stilling basin portion of the spillway was built with
reinforced conventional concrete and rock anchors anchored the stilling
basin to the underlaying bedrock.
The drainage and monitoring gallery of the dam has exposed RCC
walls with a conventional concrete floor and prefabricated steel
reinforced concrete roof lids. Foundation drains, piezometers, and
inclinometers were drilled and installed during the gallery construction.
The gallery spans approximately two-thirds the length of the dam.
RCC Mixing and Placement
RCC was produced using a portable C.S. Johnson-Ross Bandit BTRR-600
batch type plant and an IHI HyDam 4500D mixer. Although the plant
capacity is 800 tons per hour, it normally operated at a production
rate of 550 tons per hour.
RCC was delivered from the batch plant to the dam via a nearly
2,500-ft (762-m) long ROTEC conveyor belt. A ROTEC tripper and a
60-ft (18.3-m) long swinging conveyor delivered RCC to different
locations of the dam. The swinging conveyor had an elephant trunk
at the end to reduce segregation at the point of discharge.
 |
 |
| RCC Plant and Aggregates Stockpiles |
RCC Conveying and Placement |
Three different-size dozers spread the RCC in 12-inch (300-mm)
lifts. The dozers were equipped with laser-guided systems to obtain
a level surface. Where space was limited or access was difficult,
a small Komatsu D-21 was used. Elsewhere, spreading was accomplished
with a larger size John-Deere 850J dozer and a mid size Caterpillar
D5. The D5 was also used to finish grade the RCC lifts.
Horizontal surfaces exposed for more than 500 degree-hours were
considered cold joints and required spreading an approximately 3/8-inch
(10-mm) thick bedding mortar layer just prior to placement of new
RCC lift. The bedding mix contained 800 lbs of cement with a water
cement ratio of 0.59. Cold joints older than 36 hours required pressure
washing before spreading the bedding mortar.
The project specifications required the RCC to be compacted to a
minimum density of 97 percent of Theoretical Air-Free Density. A
double drum Ingersoll-Rand DD-130 and a single-drum Ingersoll-Rand
SD-100 were used to compact the RCC. Generally four passes with
the double-drum roller were sufficient to achieve the required density.
A higher number of passes was needed when using the single-drum
roller. The areas adjacent to the upstream and downstream faces
of the dam were compacted using a smaller Ingersoll-Rand DD-24.
Sections where access was difficult were compacted using plate tampers
and jumping jacks.
The RCC placement started in mid-December 2006 and was completed
in early June 2007. The placement was performed with one shift up
to the top of the gallery and then two shifts for most of the reminder
of the dam. Typically, the afternoon hours were used to set panels
and forms.
Facing Systems and Temporary Formwork
 |
| Upstream facing and details. |
A total of 2000 full size [6 ft x 16.5 ft (1.8 m x 5.0 m)] as well
as 500 half-size precast concrete panels were fabricated on site.
All panels were 5-inch (125 mm) thick and served as formwork for
RCC placement. Those installed on the upstream face were lined with
a flexible CARPI 40 mil synthetic waterproofing membrane. The panels
installed on the downstream side of the chimney section have a decorative
face for aesthetical purposes. Wood forms were used to form the
steps of the downstream side of the dam.
 |
| Training wall and steps showing conventional
concrete on right and grout enriched RCC on left. |
Grout-enriched RCC was used to give the exposed downstream steps of
the dam an improved appearance compared to typical exposed RCC. A
grout mix was prepared using a colloidal mixing plant at the proportions
of one part of portland cement to one part of water by weight. After
the RCC had been graded and prior to compaction, the grout was manually
poured over the top of the freshly placed RCC adjacent to the downstream
wood forms. Workers would then internally vibrate the grout into the
fresh RCC. Compaction of the RCC in this area was done using flat
bottom plate tampers, resulting in a smooth, aesthetically pleasing
exposed step.
RCC Quality Control
RCC Aggregates
Aggregate for RCC was crushed from Lafarge North America’s
Ballground, Ga., quarry. Graded aggregate base and No. 4 coarse
aggregate were transported to the site and stored in two separate
stockpiles near the RCC mixing plant. Aggregate gradation was performed
at three different points: at the quarry prior to transporting,
on samples obtained from the stockpiles, and on mixing plant belt
samples to check the gradation of combined aggregates. The maximum
aggregate size for the combined blend was 2 inches (50 mm). In most
cases, gradations of the blended aggregates met the specified limits
for the project.
RCC Mix
The RCC specified compressive strength was 2000 psi (14.8 MPa)
at 180 days. A complete laboratory testing program was implemented
to determine the fresh properties as well as the mechanical properties
of hardened RRC using three different mix proportions. Testing methods
included Vebe time, unit weight, air content and moisture content.
Additionally, testing to evaluate mechanical RCC properties was
done using 6 inch x 12 inch (150 mm x 300 mm) cylinders. Mechanical
tests included compressive strength, indirect tensile strength and
modulus of elasticity. Strength testing was also performed on accelerated
curing specimens and correlations were developed to predict the
28 and 180 day strengths based on earlier strength test results.
These correlations were used to forecast RCC strength during production
testing. Companion strength specimens were cured normally and tested
at ages up to 365 days.
Based on the specified strength and early test results, an RCC
mix containing 150 lb/yd3 (89 kg/m3) Type
I/II portland cement and 150 lb/yd3 (89 kg/m3)
Class F fly ash was selected. After several weeks of RCC placement,
the mix was adjusted and the following mix proportions were used
for the remainder of the project: 135 lb/yd3 (80 kg/m3)
Type I/II portland cement; 165 lb/yd3 (98 kg/m3)
Class F fly ash; 3,600 lb/yd3 (2,136 kg/m3)
crushed stone; and 225 lb/yd3 (133 kg/m3)
water. The target Vebe time was 25 ±
5 seconds.
Prior to the start of RCC placement within the dam footprint, an
on-site test section was built to validate the contractor’s
means and methods and to check the performance of RCC mixes. The
test section also provided an opportunity to train testing personnel.
Statistical analyses of production samples test results performed
in accordance with the American Concrete Institute Committee Report
214, showed very good overall variation. The accelerated curing
strength corresponding to 180–day strength for the project
averaged 3,010 psi (20.8 MPa).
A total of 218,000 yd3 (167,000 m3) of RCC
and 9,000 yd3 (6,900 m3) of conventional concrete
were placed to build this 180-ft (55-m) high dam, which is the tallest
non-federally regulated dam in Georgia. The in-place cost of RCC
was $74.67/yd3 ($97.66/m3), including the
cost of materials, mixing, transporting, placing and curing.
The initial filling is scheduled to commence in January 2008. Initial
filling is expected to take 18 months to reach normal operating
level. Creating this water supply reservoir will help fend off future
water supply crises for the rapidly growing City of Canton and for
the wholesale customers of the water authority.
Credits
Owner: The City of Canton and The Cobb County-Marietta
Water Authority, Ga.
Engineer: Schnabel Engineering, Alpharetta, Ga.
Contractors: Thalle Construction Company, Hillsborough,
N.C. and ASI Constructors, Buena Vista, Colo.
|